For semi-flush mounting, depth behind the panel should be about 7.4 inches (188.0
mm). Add about 2 inches space for wire, cable duct and so on.
Check the allowed minimum bending radius from the optical cable
manufacturer.
F
A
B
E
C
G
D
H
GUID-B6E40F1B-CA81-4527-B5EE-CB331A56E422 V1 EN
Figure 7:
Panel cutout and drilling plan for flush or semi-flush mounting
A 9.250 in. (235.0 mm)
E 6.062 in. (154.0 mm)
B 18.500 in. (469.9 mm)
F 5.562 in. (141.3 mm)
C 6 × ∅ 0.220 in. (5.6 mm) G 5.630 in. (143.0 mm)
D 17.500 in. (444.5 mm)
H 4 × R.030 (0.76) max
1.
If the IED is with rack mounting brackets on either side, loosen the four #6-32 fixing
screws and remove the brackets. Store them away as spares or for future use.
2.
Remove the set screws from the top of the case.
3.
Slip the bezel frame over the IED case with flange towards the front of the case.
Adjust the position where the bezel has to be fixed as appropriate for flush or semi-
flush mounting.