7.4
Changing the IED functionality
7.4.1
Defining the setting group
GUID-A9853F1B-78ED-4AEF-AAE2-C27FF3DAE408 v3
Do not switch off the auxiliary power supply to the IED before
changes, for example, setting parameter or local/remote control
state changes are saved.
Do not switch off the auxiliary power supply to the IED before
changes. For example, when setting parameter changes are saved.
7.4.1.1
Activating a setting group
AMU0600439 v8
IED settings are planned in advance for different operation conditions by
calculating setting values to different setting groups. The active setting group can
be changed manually from the menu or by the PCM600 tool.
1.
Select
Main menu/Settings/Active setting group/SETGRPS:1
and press
.
IEC13000235-1-en.vsd
GUID-9BC3D595-CF08-42AF-B74E-0D3970A552DB V1 EN-US
Figure 44:
Active setting group
2.
Select the setting group with
or
.
3.
Press
to confirm the selection or
to cancel.
4.
Commit the settings.
Section 7
1MRK 500 128-UEN B
Operating procedures
70
650 series 2.2 IEC
Operation manual