![ABB Relion 630 Series Скачать руководство пользователя страница 138](http://html1.mh-extra.com/html/abb/relion-630-series/relion-630-series_engineering-manual_3428217138.webp)
9.3
Configuring DNP3 protocol signals
1.
Save the actual project configuration in PCM600 to make all signals visible for
Configuration Management tool.
Direct configured hardware channels in the application
configuration appear in CMT. Do not configure these hardware
channels to be sent by DNP3 as they are not event-handled.
IEC10000172.vsd
IEC10000172 V1 EN
Figure 102:
Configuring hardware channels directly to the function blocks
GUID-FF46FEE9-FEA6-4E29-A6D4-039148A9FB32 V1 EN
Figure 103:
CMT: Hardware channels appearing in the Communication
Management Tool
2.
Right-click the IED in the plant structure and select
Communication
Management
to start the Communication management tool.
3.
Select the DNP3 protocol from the new window and click
OK
.
presents the design of the two container windows, which open after the selection
of DNP3.
Section 9
1MRS756800 F
DNP3 communication engineering
132
630 series
Engineering Manual