76
Fuse failure supervision (FUSE)
Chapter 10
Verifying settings by secondary
injection
10. Keep the current constant. Disconnect the voltage in all three
phases simultaneously.
The FUSE-VTSU, FUSE-VTSZ and FUSE-VTF3PH signals
should not appear.
8.5
Completing the test
Continue to test another function or complete the test by setting the test mode to off.