Checking the installation of the inverter station
Item
Check all mechanical operating functions by operating them twice.
Check that the paint is not damaged. Damaged areas must be repaired according to the instructions.
Check that all cable inlets are securely installed. Check that unused cable openings are protected
with protection caps.
Check that the weather protection hoods are installed and that nothing is restricting airflow through
air inlets and outlets.
Check the earthing (grounding) of the inverter station and its components against the earthing
(grounding) schematic. Pull the earthing wires at the terminals to ensure that the connections are
tight.
Remove all foreign objects such as loose fastenings or tools from the station. They can cause
shortcircuit faults or other damage.
Check that the station is clean. Mud on painted surfaces will increase the risk of corrosion. See
chapter
.
Check the main circuit clearance distances, cable terminations and connections against the main
circuit diagram. Check that all connections have been tightened.
Check that all necessary warning labels have been attached to the inverter station. For example,
labels in the local language or required by local regulations.
Check that the insulation resistances of the external power cables have been measured. See section
Measuring the insulation resistance of the cabling (page 34)
Perform the installation checks detailed in the device-specific manuals. See section
for a list of manuals.
Carry out the inspection procedures required by the respective authorities.
32 Checking the installation
Содержание PVS800-IS
Страница 1: ... ABB CENTRAL INVERTERS PVS800 IS inverter stations 1 645 to 4 156 MW Hardware manual ...
Страница 2: ......
Страница 4: ......
Страница 8: ...8 ...
Страница 12: ...12 ...
Страница 20: ...20 ...
Страница 24: ...24 ...
Страница 44: ...44 ...
Страница 65: ......
Страница 66: ......
Страница 67: ......