3.2 Inspection work
Inspection work includes preventive visual controls plus monitoring and
measuring work before and during commissioning. Inspections help de-
tect changes to the turbocharger. Machine damage can be avoided.
3.2.1
Inspection before commissioning
Monitoring devices
u
Check for correct functioning.
Filter mat
u
Inspect for damage.
Lubricating system
u
Check oil filter for cleanliness before commissioning.
CAUTION
Contaminated oil
Particles of dirt and solid matter in the oil can cause serious damage to
the machine or property.
u
During initial commissioning and after all service work, the complete
lubricating system must be flushed thoroughly with warm oil.
u
When running in the engine and after all service work on the lubricat-
ing system, special running-in filters must be used.
u
Check oil pressure in oil supply lines.
CAUTION
Prelubrication
Serious machine or property damage might result if the turbocharger is
not supplied with oil when the engine is starting.
u
Activate prelubrication device before starting engine.
Warning plates on tur-
bocharger
u
Check whether the warning plates are present and legible.
u
Check whether the protective sheets have been removed.
TPL65: Version with compressor wheel cooling system
u
Check whether compressor wheel cooling system is fitted to bearing
casing.