Action
Make sure that it is safe to connect voltage:
• nobody is working on the unit or circuits that are wired from outside into the cabinets
• covers of the motor terminal boxes are on
• cabinet doors are closed
• the disconnecting device [Q1] is open.
Drive with the earthing/grounding switch [Q9] (F259): Open the earthing/grounding switch.
Close the auxiliary voltage switch [Q21].
■
Setting the supply unit parameters
Action
If the supply unit includes one supply module:
• Check the correct voltage ranges by parameter
195.01 Supply voltage
.
• Reboot the control unit by parameter
196.08 Control board boot
.
If the supply unit includes more than one supply module: Make sure that the value of parameter
195.31
Parallel connection rating id
corresponds to the actual number of parallel-connected diode supply
modules:
• Select the correct voltage range with parameter
195.30 Parallel type filter
.
• Select the correct supply unit type with parameter
195.31 Parallel connection rating id
.
• Reboot the control unit by parameter
196.08 Control board boot
.
• Check the correct voltage range, parameter
195.01 Supply voltage
.
• Reboot the control unit by parameter
196.08 Control board boot
.
If you need more information on the use of the control panel, see
ACX-AP-x assistant control panels
user's manual
(3AUA0000085685 [English]).
■
Powering up the drive
Action
Close the disconnecting device of the supply unit.
Drive with main breaker [Q1] (F255): Unlock the withdrawn breaker, and crank it in.
WARNING!
Never use the start button of the air circuit breaker to close it. Start button bypasses normal
start-up procedure and may damage the module.
Make sure that the control panel [A59] is in the remote mode (Loc/Rem key of the panel).
Switch the Run enable and Start signals at digital input DI2 on (1) to start the operation of the supply
unit.
Turn the operating switch [S21] on the cabinet door to ENABLE/RUN (1) position.
Run enable starts the supply unit power up sequence. After the program has stepped through it (ap-
proximately 3 seconds), the drive DC link is charged, the main breaker is closed and the supply unit
is in operation and ready to the supply inverters.
Turn the operating switch [S21] to
on
(1) position to activate the Run enable signal and to close the
main breaker [Q1].
Start-up 61
12
Содержание ACS880-307LC
Страница 1: ... ABB INDUSTRIAL DRIVES ACS880 307LC diode supply units Hardware manual ...
Страница 2: ......
Страница 4: ......
Страница 12: ...12 ...
Страница 34: ...34 ...
Страница 40: ...11 Reinstall the shrouding removed earlier 12 Close the door 3 PE PE 40 Electrical installation ...
Страница 41: ...10 9 7 6 8 Electrical installation 41 11 ...
Страница 73: ...11 12 12 6 10 Maintenance 73 ...
Страница 78: ...78 ...
Страница 88: ...88 ...
Страница 96: ... 400 mm wide input cubicle 96 Technical data ...
Страница 97: ... 600 mm wide incoming cubicle or input cubicle Technical data 97 ...