24 Standard Commissioning Process
Commissioning third-party equipments
If third party equipment has to be commissioned by an ABB commissioning engineer, the
scope of the work involved and the responsibilities must be agreed by contract and the
commissioning engineer must be informed accordingly.
If the equipment mentioned in the following sections is not commissioned by an ABB
commissioning engineer, confirmation that the equipment has been tested and is ready for
operation must be obtained from the responsible person.
In DriveStartup:
It is necessary that the steps are reviewed when checking third-party
equipment and that each item is checked off before the commissioning has been
completed.
Main circuit breaker (MCB)
The main circuit breaker is commissioned and the insulation tests are performed according
to the manufacturer’s documentation.
The signed MCB commissioning report must be received from the responsible person.
The correct operation of the MCB will be tested before the MCB is used to supply the main
power to the converter. The test is performed with the MCB in test position.
Information on the required control interface to the converter and on the breaking time of
the circuit breaker can be obtained from the
ACS580MV Engineering Guideline
(2UBB013672) and the converter wiring diagrams.
The following has to be checked:
•
It is forbidden to set common point for open status, close status and ready status
signals.
•
The MCB must open once the auxiliary power is removed. If the MCB is equipped with
under voltage trip coil.
•
The MCB is commissioned and the insulation tests are performed according to the
documentation of the manufacturer (The signed MCB commissioning report must be
received from the responsible person).
Power cables
The insulation resistance must be measured or the confirmation of the measurement must
be obtained.
In case measurement has to be performed by the service engineer, please refer to
NOTICE
For later tests, motor and driven equipment is recommended to be uncoupled.
NOTICE
The field engineer should confirm that the power cables are connected to the
correct bus bars before switching on the main power. Once the main power direct reach
the output bus bars by wrong connections, the power modules would be irreversible
damaged.
Содержание ACS580MV
Страница 1: ... ABB INDUSTRIAL DRIVES ACS580MV Commissioning Manual 200kW to 6300 kW 3 3kV to 11 kV ...
Страница 4: ......
Страница 8: ...8 ...
Страница 43: ...Standard Commissioning Process 43 Press the button Load SW and wait till update is finished ...
Страница 45: ...Standard Commissioning Process 45 In this step should select Lab Tools Standalone Installation ...
Страница 60: ...60 Standard Commissioning Process Complete the installation press Finish ...
Страница 83: ...Standard Commissioning Process 83 ...
Страница 96: ...96 Standard Commissioning Process ...
Страница 121: ...Option 121 IO signals ...
Страница 122: ...122 Option Panel control interface System fault ...
Страница 140: ...140 Option ...
Страница 148: ...148 Preventive Maintenance ...