46
“Operation and installation manual”
EN
6.1.3 Remove the base cover - Terra 60
B
B
A
• Take the base and remove the 4 screws (A)
• Remove the base covers (B)
6.1.4 Open the cable glands - Terra 60
A
B
C
A
A
B
• Open the necessary cable glands for the cables:
−
AC input cables L1, L2, L3 and Neutral (A). Cable diameter
accepted 27...35 mm.
−
Protective Earth (PE) cables (C). Cable diameter accepted
19...28 mm.
NOTE
The installation of a second PE cable should
be required by local rules.
−
Ethernet or signals cables (B). Cable diameter accepted
8...13 mm.
6.1.5 Route the cables - Terra 60
• Put the cables L1, L2, L3 and Neutral through the cable
inlets. Apply the full cable slack of 350 mm.
• Put the PE cable through the cable guide plate. Apply
the full cable slack of 350 mm.
• If there is an ethernet cable, then put it through the cable
guide plate. Apply the full cable slack of 500 mm.