www.a-ts.cn A-TS Technology
FT50
26
be less than 0.6G. Make sure to stay away from the punching machine and such equipment.
4) Do not install the frequency converter in a place with direct sunlight, high humidity, or water
drop.
5) Do not install the frequency converter in a place with corrosive, flammable, or explosive gas
in the air.
6) Don't install the frequency converter in a place with greasy dirt and dust.
3.1.3 Installation Space
To ensure the normal operation of the frequency converter, enough space must be reserved
before installation to ensure good heat dissipation. For single machine installation, please refer
to Figure 3-1, 3-2 and Table 3-1, 3-2 to reserve the space around the frequency converter.
Table 3-1 Single machine installation space requirement (2.2kW-160kW)
Power Level
(kW)
Space Requirement (mm)
A1
B1
C1
2.2-22
≥10
≥200
≥40
30-37
≥50
≥200
≥40
45-55
≥50
≥300
≥40
75-110
≥50
≥300
≥40
132-160
≥50
≥300
≥40
Vertically upward
Figure 3-1 Single machine installation space requirement (2.2kW-160kW)
Table 3-2 Single machine installation space requirement (200kW-355kW)
Power Level
(kW)
Space Requirement (mm)
A2
B1
B2
C2
D
200-220
≥10
≥350
≥250
≥20
≥20
250-280
≥10
≥400
≥250
≥20
≥20
315-355
≥10
≥450
≥250
≥20
≥20