manualshive.com logo in svg
background image

LIEBERT® EXS™ UPS 

208/220­‑V­30­KVA

Quick Installation Guide

590-1971-501A/SL-70330_REV0

   

 1

IMPORTANT:

 Before installing, 

connecting to supply or operating 

your Liebert EXS UPS, please 

review the Safety and Regulatory 

Statements sheet. For detailed 

installation, operating, maintenance 

and troubleshooting information 

visit the EXS product page for the 

EXS Installer/User Guide available 

at www.Vertiv.com or use the QR 

code below.

INSTALLATION 
Inspecting the UPS

Inspect the UPS for any signs of 

obvious damage. If damage is 

visible, do not proceed. File a 

damage claim with the carrier 

immediately and send a copy to:

Vertiv Corporation

1050 Dearborn Drive

P.O. Box 29186

Columbus OH 43085

Attn. Traffic Department

Choosing a location

The UPS measures 23.6 x 33.5 x 

63 in. (600 x 850 x 1600 mm). 

Install the UPS in a clean, well-

ventilated environment with the 

ambient temperature range of 32°F 

to 104°F (0°C to 40°C).  

For installation and maintenance, 

3 ft (914 mm) clearance is required 

in the front and rear of the unit. For 

proper ventilation during normal 

operation, leave 8 in. (203 mm) 

clearance on the rear. No side 

clearance is required for installation 

or operation of the UPS.

Handling and unpacking    

the unit

The unit weighs up to 1,650 lb 

(748 kg), depending on the number 

of batteries included. The UPS 

ships on a pallet and is equipped 

with casters that permit two or 

more people to roll it off the pallet 

for installation. Use a forklift or 

pallet jack to move the palleted 

UPS as close as possible to the 

installation location before 

removing packing material or 

loosening shipping brackets.
1. Remove the protective

packaging, shown in the

illustration at the top-right.

2. Locate the accessories

package on top of the UPS and

set aside.

3. Use a 16-mm (5/8 -in.) wrench

or socket to un-bolt the

shipping brackets from the

pallet.

4. Un-bolt the shipping brackets

from the front and rear of the

UPS. Remove the front lower

panel from the UPS to remove

the front bracket.

5. Make sure the leveling feet are

raised so they do not interfere

when rolling the unit on the

casters.

6. Roll the unit down the ramp to

the installation location, see

the illustration above, then

lower the leveling feet to fix the

UPS in the install location.

Repositioned ramp 

placed for unit 

transfer to 

installation location

Removing Packaging and Moving the UPS

Ramp in 

shipping position

Packaging

Отзывы: