Summary of Contents for ROBOJETFLOSS ACB-09-120

Page 1: ......

Page 2: ...COTTON CANDY MACHINE ACB 09 120 rev 11 May 18 OPERATION MANUAL COTTON CANDY MACHINES ROBOJETFLOSS ACB 09 120 ROBOJETFLOSS PRO ACB 09 120 PRO ROBOJETFLOSS RENT ACB 09 120 R 2018 2 ...

Page 3: ...l 6 Avoid OVERHEATING motor should rest 15 min per hour of operation 7 Do not MODIFY the design of the machine 8 UNPLUG the power cord before cleaning or servicing In accordance to EN 60335 1 2012 standard the machine can be used by children aged 8 years and above and persons with reduced physical sensory or mental capabilities or lack of experience and knowledge if they have been given supervisio...

Page 4: ...tart time 60 sec 20 sec 60 sec Spinning rate 3300 rpm 3300 rpm 3300 rpm Rated current not more 16 A 16 A 12 A Rated voltage 120V 60Hz 120V 60Hz 120V 60Hz Dimensions machine only 15x16x15 in 15x16x15 in 15x16x15 in Dimensions pan included 26x26x19 in 26x26x19 in 26x26x19 in Weight not more 33 lbs 33 lbs 33 lbs The RoboJetFloss will produce results at ambient temperatures up to 104 F 41 C with relat...

Page 5: ...FOR SAFE OPERATION Plastic aluminum floss pan dimensions are 27 x 27 x 10 with net weight of 3 3 and 4 4 lbs respectively 1 4 MACHINE DESIGN AND OPERATION PRINCIPLE The RoboJetFloss includes the following main components Housing 1 Chassis 2 with electric motor and Spinning Head 3 The spinning head and electric motor are mounted on the chassis which itself is connected to the housing by four spring...

Page 6: ......

Page 7: ...t Knob 13 regulates power to the heating element and thus controls its temperature Voltmeter 14 indicates actual voltage supplied to the heating element The PRO version includes a Quick Start button 15 which temporarily sends maximum power to the heating element even when the electric motor is not running See the figure above for ACB 09 120 front panel Appearance may vary depending on your specifi...

Page 8: ...ler There is a 16A circuit breaker provided for short circuit protection 2 2 PREMISES REQUIREMENTS The equipment may be operated in temperatures ranging from 41 F to 104 F with relative humidity not exceeding 50 at 104 F 2 3 RAW MATERIAL REQUIREMENTS Use only 100 pure sugar beet or cane with flossine or ready to use flossugar Do not use sugars with starch dextrose or similar additives as they can ...

Page 9: ......

Page 10: ......

Page 11: ......

Page 12: ... heating element and can be done whether the main power switch is on or not This will substantially reduce the time required to begin candy production Owners of the standard version can achieve a similar result by manually adjusting the voltage regulator After switching on both the motor 11 and heating element 12 an experienced operator can adjust the voltage regulator to the maximum 13 But again ...

Page 13: ...pe than a wide sleeve Keep in mind that once the heating element and sidewall have reached such a high temperature reducing the voltage will not immediately produce the desired effect Due to thermal lag any changes in voltage will only slowly take effect over the next 15 to 30 seconds or longer depending on ambient temperatures so it is very important to avoid overheating the element in the first ...

Page 14: ...head at least 1 3 full at all times will prevent this from occurring Finally if the coil and sidewall become extremely overheated then brunt sugar flecks and dust will be produced instead Paying attention to Voltage regulation and not excessively preheating the coil during cold startup will ensure this does not happen Regardless of the cause you can prevent the distribution of snow which can creat...

Page 15: ......

Page 16: ......

Page 17: ...ar in the spinning head Turn off power to the heating element switch 12 and capture the remaining cotton candy as the head cools down When the coil cools to the point that snow is produced then cover the head with the No Snow tool and allow the head spin for 5 7 minutes to fully cool down before turning off the main power switch 11 Once cool to the touch wipe out the inside of the No Snow tool and...

Page 18: ...ce section below Do not leave unused flossugar in the spinning head for more than a day or two as it can harden caramelize and effect the balance of the head during future sessions which could ultimately result in failure of the machine During transportation always secure the chassis using the transportation lock down nuts This will prevent possible damage of the machine and prolong the lifetime 1...

Page 19: ...le3 is recommended PROCEDURE PERIOD Cleaning machine and pan surfaces removing sugar and cotton candy Once a day Sidewall and heater cleaning Twice a month Brush unit maintenance Every 6 months 3 2 SAFETY MEASURES DO NOT CLEAN THE SPINNING HEAD OR COMPONENTS WITH SHARP OR METAL PARTS HOT WATER A SPONGE OR SOFT BRISTLE BRUSH IS ALL THAT IS REQUIRED OR PERMITTED DISCONNECT THE POWER SUPPLY BEFORE CL...

Page 20: ......

Page 21: ...eparate the heater coil from the sidewall to clean the areas where they contact one another DO NOT IMMERSE HEATING ELEMENT TERMINAL LEADS IN WATER AS THIS MAY CAUSE FAILURE 6 The sidewall and heating element must be dry before reinstalling ABRASIVE OR MECHANICAL CLEANING OF HEATING ELEMENT AND SIDEWALL IS PROHIBITED Re assembly of the spinning head is done in the reverse order Once completed turn ...

Page 22: ......

Page 23: ...COTTON CANDY MACHINE ACB 09 120 rev 11 May 18 3 4 STORAGE If the unit is not used for a prolonged period of time then the routine maintenance must be performed before it is placed back into service 23 ...

Page 24: ...heck the heating element replace if necessary Brush unit damage Check the brush unit Brushes must fit closely to the slip rings without sparking Replace the brush unit if necessary Low productivity Caramel sticking on the sidewall Clean the sidewall and heating element in accordance with instructions Low voltage from the outlet Check the voltage from the outlet or extension cord Low voltage is a f...

Page 25: ...1 F 5 TEST CERTIFICATE ACB 09 120 machine has met mandatory requirements of the state standards actual technical documentation and approved for use TEST CERTIFICATE ACB 09 120 Product Name _____________ Serial No The equipment is made with accordance to mandatory requirements of the state standards actual technical documentation and approved for use QC Engineer STAMP HERE _________________ Signatu...

Page 26: ...can be changed by manufacturer at any time due to improvements and or other reasons Technical specifications stated in this document are intended to act as a reference point which is necessary to evaluate suitability of the equipment for the customer s needs and are not the subject of warranty policy The information stated in this document has been thoroughly checked and considered as accurate one...