IMPORTANT:

INSTALLATION NOTES

PLUMBING

Follow Local Plumbing Codes

We strongly recommend to have a professional plumber
to do the plumbing installations

Tools and Materials required:

Tools:

Materials:

Deck mounted faucet and fill spout.

INSTALLATION

Bathtub installation

Tub Leveling

NOTE:

Floor Opening

The Azzura Free Standing Acrylic Bathtubs

are carefully inspected and packed for shipment. You should
check your unit and if there are any problems contact your
dealer before installation.
Protect the bathtub and fittings from dirt and damage by
leaving the polyethylene protective film in place until
installation and other related construction are complete.

All plumbing and drainage have to be installed before
securing the tub to ensure correct position.
Note that the drain-overflow assembly may extend below the
bottom of the bath and may require a cutout in the floor.

.

Before drilling any holes in the floor, make sure there are no
hidden structural elements underneath of the floor. Although
the waste and overflow may be factory located, it is the
responsibility of the plumber / installer to seal and inspect
unit before installation.

Mirolin Industries does not warrant leaks related to improper

installation of waste and overflow.

Electrical Drill, Hole Saw, Measuring tape, Pencil,

Screwdriver, Level, Safety glasses

Silicone Sealant, Epoxy or Construction

Adhesive

Use a high-speed drill

or a hole saw for drilling the top surface of the bath for deck-
mounted faucet and fill spout. Mask the surrounding surface
to prevent scratches and other damage during drilling. Follow
the faucet manufacturer's instructions for the size and

spacing for the hole required. Locate the fill spout so that the
water runs into the bath without striking or splashing the
deck, handrails or overflow.

It is recommended that the installation be done by two
people.
It is recommended that the skirt be approximately 1/8”
above the floor. The skirt has no structural strength and
is not designed to support the bathtub.
For anchoring the legs of the bathtub to the floor use
2 part epoxy cement or construction adhesive

Lay bathtub upside down on a blanket or cardboard to
protect the acrylic surface. Adjust the feet so that they are
1/8” above the top of the skirt. This will ensure no weight is
on the skirt of the bathtub.

The bath must be level along the top edges in both directions
to ensure proper drainage.
The bath is factory leveled. If an adjustment is required, the
freestanding tubs have adjustable feet with locknuts.
Place the tub where it is to be installed and adjust the
adjustable legs to make sure the tub is level.
After the level has been set, tighten the nut in a new position.
This will secure the feet in a place so that they do not move.

Determine the location of the bathtub which allows enough
space for plumbing and making sure that the drain and
plumbing are not directly above the floor joists. Access is
required to tighten and service plumbing after installation.

Mark the plumbing fixtures location. Cut or drill the floor.

The floor must be leveled prior to setting the tub

in final position.

INSTALLATION INSTRUCTIONS AND OWNER’S MANUAL

READ ALL INSTRUCTIONS CAREFULLY BEFORE STARTING THE

INSTALLATION

PLEASE RECORD THE SERIAL NUMBER ________________ OF YOUR

BATHTUB AND SAVE THIS MANUAL FOR FUTURE REFERENCE

INSTALLATION INSTRUCTIONS

FREE STANDING ACRYLIC BATHTUBS

1

©

Copyright 2010

The Copyright includes all content on the document.

Mirolin Ind.

Reviews: