Page 1: ...Eclipse BrightFire 200 Burners BRT Size G M and B Version 1 Operating Instructions Edition 09 15...

Page 2: ...and Eclipse will not be liable for any other injury loss damage or expenses whether direct or consequential including but not limited to loss of use income or damage to material arising in connection...

Page 3: ...l of Components 6 BrightFire 200 Adjustable Burners 7 Gimbal Mounting Bracket Installation 7 Pre Start Considerations 7 BrightFire 200 Installation and Start Up During Initial Heat Up Furnace 8 Bright...

Page 4: ...ncreased flame control and burner flexibility Lower NOX emissions Compatible with current mounting bracket for easy installation Compatible with current BrightFire gas and cool ing air connections for...

Page 5: ...er equipment installed under the furnace port Eclipse recommends installing a safety guard around moving parts Eclipse recommends considering any area with moving mechanical parts a restricted area Th...

Page 6: ...ks from UL FM CSA European EN 746 2 with CE mark from TuV Gastec Advantica Electrical Wiring All the electrical wiring must comply with all applicable local codes and or standards such as NFPA Standar...

Page 7: ...termined from the furnace and port information Gimbal Mounting Bracket Installation NOTE For additional info on the Gimbal Mounting Bracket refer to Info Guide 1113 1 Set all bracket adjustments to ze...

Page 8: ...main burners is increased the heat up burner input is decreased to maintain the heat up schedule until the heat up burner can be removed Figure 3 1 Typical Installation Under port Figure 3 2 Typical...

Page 9: ...ngement incorporates two burners per port Both burners of any given port should have equal gas flow and be adjusted in pairs when balancing gas flow On a typical under port fired furnace either side p...

Page 10: ...et the main gas flow control to manual and open to 10 15 7 Establish gas and cooling air supply up to the local shut off valves 8 Beginning with one burner on the off firing side of the furnace discon...

Page 11: ...tation of the adjustment knob will lengthen the flame while moving the adjustment forward clockwise rotation of the adjustment knob will shorten the flame To read the indicator rod positions for the a...

Page 12: ...ed further from the port opening while maintaining lower NOX emissions Converting BrightFire 200 from Gas to Oil Firing NOTE If firing heavy fuel oil the oil must be conditioned to maintain a viscosit...

Page 13: ...ate plugging of the regenerator ports instrumentation issues or furnace wear allowing infiltration of ambient air A side to side bias in the ratios may be required 5 Check the rear packing nuts to ver...

Page 14: ...and nut but do not tighten 20 Insert the inner gas tube through the rear of the burner until the end is flush with the area adjustment lug 21 Tighten the inner gas tube locking nut and the packing gla...

Page 15: ...illimeter mm inch in 3 94 x 10 2 MJ Nm Btu ft standard 26 86 From To Multiply By kiloPascals kPa millibar mbar 10 meter m millimeter mm 1000 millibar mbar kiloPascals kPa 0 1 millimeter mm meter m 0 0...