background image

1

Revision date: 08.22.13

©2013 ClearSpan™

All Rights Reserved. Reproduction 

is prohibited without permission.

Diagram shows a sample end panel kit for a frame. Actual panel positions and sizes for your end panel package may 

differ from what is shown. Photo is used as an example only. Consult the diagrams in the Quick Start section of this 

guide for your building to see the panel sizes and layout.

ClearSpan

 

Twin-Wall Polycarbonate End Panel Kit 

20' Wide & 24' Wide

STK#         

R020B00008 (20' Wide)
R024B00008 (24' Wide)

Summary of Contents for R020B00008

Page 1: ... frame Actual panel positions and sizes for your end panel package may differ from what is shown Photo is used as an example only Consult the diagrams in the Quick Start section of this guide for your building to see the panel sizes and layout ClearSpan Twin Wall Polycarbonate End Panel Kit 20 Wide 24 Wide STK R020B00008 20 Wide R024B00008 24 Wide ...

Page 2: ...llows for the placement of panels as determined by the position of the door or doors It is the responsibility of the owner contractor to adjust the position of the end panels based on the end frame and the position of the installed door or doors Consult the services of a qualified contractor to install the panels if needed IMPORTANT Some diagrams throughout this manual show the outside edges of th...

Page 3: ...must seek the help of a qualified contractor REQUIRED TOOLS The following list identifies the main tools needed to assemble the end wall Additional tools and supports may be needed depending on the structure location and application Tape measure or measuring device Fine point marker to mark the location on frame and panels Variable speed drill and impact driver cordless with extra batteries works ...

Page 4: ...me parts are not shown UNPACK AND IDENTIFY PARTS The following steps will ensure that you have all the necessary parts before you begin to install the end panels Unpack the contents of the shipment and place 1 where you can easily inventory the parts Refer to the Bill of Materials Spec Sheets Verify that all parts listed on the Bill of Materials Spec 2 Sheets are present If anything is missing or ...

Page 5: ...t section for the location and lengths of each panel The diagrams are located at the back of these instructions ATTENTION Position panels as shown on the panel diagrams Using a panel in the incorrect place can affect the placement of subsequent panels In addition the amount of aluminum profile used between panels may not be adequate if additional seams are created Install all accessories fans vent...

Page 6: ...stall the next panel See diagrams on this page For the 20 wide frame install all remaining panels and continue with Step 16 For the 24 wide frame continue with Step 7 Diagram below shows the 24 wide end wall Actual end frame and panels may differ from frame shown The installation of doors also will affect panel installation and position Consult the panel diagrams located in the Quick Start section...

Page 7: ...e 108867 end cap the H channel when installed properly is positioned under the end cap Set the panel back in place 12 with the UV protected side facing to the outside against the end wall and install the H channel along the edges Greenhouse frames only Position the top end of the side H channel under the lip of the end cap and onto the polycarbonate panel Verify that the panel is square and in the...

Page 8: ...ach corner of the building Measure and cut a section of 104213 profile and install it 16 along the outside edge of each outer panel to complete installation see drawing C Install a Tek screw to secure the H channel to the frame in 17 each place where H channel crosses the end wall brace See letter D in the diagram below for an example Continue by reading the care and maintenance section 18 GROUND ...

Page 9: ...good condition Replace damaged panels if needed Check connections and all fasteners to verify that they remain tight Check the contents of the shelter to verify that nothing is touching the polycarbonate panels that could cause damage Inspect the end wall frequently and regularly to ensure that it remains secure and in good repair Replace broken or missing components immediately If the shelter is ...

Page 10: ... panels meet the sidewall panels and create a finished corner Diagrams in this section include sidewalls Ground Level Install Tek screws and washers through the panel and into the end wall brace Evenly space the screws at 12 6 x 10 Panel 102529 6 x 12 Panel 6 x 10 Panel Panel Kit for 20 Wide Frame R020B00008 GROUND LEVEL 4 x 8 Panel 102908 4 x 12 Panel 102532 4 x 12 Panel 6 x 10 Panel 6 x 10 Panel...

Page 11: ...he top edges of the upper panels after these are cut to fit Tape the top and bottom of the outer panels marked with an X All polycarbonate panels to be installed with UV protected surface toward the outside of the shelter X X Install 104213 profile along this edge of the end panel Install 104213 profile along this edge of the end panel Remember to position and trim the outer panel so it meets the ...

Page 12: ...iagram below shows the installed sidewall hat channel used for the installation of the sidewall polycarbonate panels of the main building All polycarbonate panels to be installed with UV protected surface toward the outside of the shelter X X X X X X Install 104213 profile along this edge of the end panel Install 104213 profile along this edge of the end panel Remember to position and trim the out...

Page 13: ...13 Revision date 08 22 13 Notes This page is reserved for customer notes ...

Reviews: