Figure 5-27 A Fixed Cabinet
Note:
To install multiple cabinets, after positioning the first row of cabinets, adjust and fix the
outmost cabinet, adjust and fix other cabinets one by one according to the first one.
Then install the second and third rows of cabinets.
4.
Clean the ground.
– End of Steps –
5.3.5 Insulation Test
Context
The insulation test should be conducted after each cabinet feet is fixed, so as to avoid
unnecessary workload after the insulation test is found unqualified at a later stage of the
installation.
Steps
1.
Set the multimeter to the resistor side.
2.
Use its two measure probes to contact the metal part of the cabinet footing and the
expansion bolt to measure the resistance. If the circuit is in the disconnected state,
insulation test is complete. If no disconnection, go on with the next step.
3.
Check whether insulation sleeve is missing or damaged. If yes, the user shall repeat
the previous procedure (to fix the cabinet), then redo the insulation test.
– End of Steps –
5-20
SJ-20110531095035-004|2011-10-28 (R2.0)
ZTE Proprietary and Confidential
Summary of Contents for ZXG10 iBSC
Page 8: ...II ...
Page 167: ...Figures Figure 11 7 Step 3 of Board Unplugging 11 5 V ...