ZXG10 iBSC Hardware Installation Guide
Figure 5-2 Cabinet Installation Flow
5.2 Base Installation Mode
This mode is applicable on the anti-static floor. Both the base and the installation rack
base support the cabinet.
Fasten the base on the cement floor with expansion bolts, and fix the installation rack
base with the base through bolts. The cabinet slides into the installation rack base through
the frame on the base and then fixed on the rack base with bolts. A cabinet needs two
installation bases.
Make sure that the distance between the cabinet bottom and the upper surface of the
anti-static floor is greater than 10 mm after the installation so that the door of the cabinet
can be opened normally.
The base height can be adjusted in the unit of 25 mm. Refer to the installation instruction
for the base installation. Installation engineers can choose the base type according to the
height of the anti-static floor.
5.2.1 Required Parts
1.
ZXG10 iBSC rack, its profile shown in
5-4
SJ-20110531095035-004|2011-10-28 (R2.0)
ZTE Proprietary and Confidential