background image

                          Fixed Hoist Test Facility Operation and Maintenance Manual        ZOM-12000-9 rev 0 

 

Zephyr International LLC  *5015 Enoch Rd, Conway SC 29526  * Phone 843-365-2675 *Fax 843-365-2677 

Email  

[email protected]*

 Web 

www.zephyrintl.com

  * 

Serving Helicopter Rescue Hoist Users Worldwide 

  Copyright 2010 

 

Operating Procedure     

BL-29900

 

 

Start Up 
 

1.  Install Hanging Hoist Mount, Arm using the pins and retaining pins 

2.  Install hoist on mount using the pins and retaining pins 

3.  Raise mount into position, install the pins in the load cells, lower chain hoist to apply 

the load to the lead cells 

4.  Attach the Electrical harness connectors 

5.  Attach the 400Hz power cable to the receptacle 

6.  Turn on the 3 phase 400 hz power switch 

7.  Position the Zephyr RHGSE under hoist 

8.  Turn the Power switch on the control box to on, the load indicator should illuminate 

9.  Activate the hoist select switch on the control box to select the BL-29900 hoist 

10. Press the Tare button on the load display to zero out the load with no load on the 

cable 

11. Operate the hoist using pendant, or pilot override  

12. Attach the rescue hoist cable to the Zephyr RHGSE and operate the hoist in the 

down direction 

13. Follow the operating instructions for the Zephyr RHGSE while running the hoist 

 

 

Reviews: