Main Document Only.
29/50
Identification: MD-AL-GI-00
Rev. 1.0 07.06.21 - Application: GID
Connext User Manual
Rev. 1.2 07/06/2021
Figure 21 –Insertion of sensor to measure three-phase photovoltaic production from systems not branded
Azzurro
The figure shows the direction of the arrow found on the current
sensor. Pay attention to the insertion direction
Note
4.4.3.
Sensor for measuring 1-phase grid exchanges
If there is no storage system inverter belonging to the Azzurro brand and the grid exchange needs
to be measured, it is necessary to install an accessory sensor (ZSM-ACC-TA).
The sensor must be placed directly on the output of the exchange meter and connected to the
Connext system via pins 23 and 24 of the 24-pin terminal block, as indicated below.
Sensor cable
24-pin terminal block
Black cable
23
Red cable
24
Table 15 - exchange sensor connections
Figure 22 – Sensor insertion for measuring exchanges with the grid