Checking the correct installation of the Meter
Check the Meter on Exchange
To carry out this check, it is necessary to:
Switch off the hybrid inverter and any other source of photovoltaic production,
Switch on loads of more than 1 kW for each of the three phases of the system.
Stand in front of the meter and use the “→” keys to scroll through the items, and “ESC” to go back,
checking that:
1.
The Power Factor values for each phase Fa, Fb and Fc (phase shift between voltage and
current) are between 0.8-1.0. If the value is lower, move the sensor to one of the other two
phases until the value is between 0.8-1.0.
2.
The Pa, Pb and Pc Powers are:
Greater than 1 kW.
In line with the home consumption.
The sign in front of each negative value (–).