ST950S Plus+ Installation and Commissioning Manual
Figure 68. Cell and Label
Cell and Label in fitted
Important:
Ensure that during commissioning any battery isolation strip is removed.
Important:
Check the time reported by the controller after inserting new battery and correct if necessary.
Important:
Where the controller is connected to a network and configured to use NTP the clock will
automatically be set when the controller synchronizes to the NTP server
6.9.3. Loading IC4 Configuration
The ST950 controller requires an IC4 configuration to be loaded for correct operation. Configurations
can be loaded by using;
•
Status and Configuration → Controller → IC4 Config → Import Config web page
Full details on how to load and confirm IC4 configuration can be found in the ST950 User Interface
Handbook 667/HU/46000/000.
After loading an IC4 configuration, which is significantly different from that previously in use, it will be
necessary to own the Heart. This can be performed by using;
•
Status and Configuration → Controller → Heart → Ownership web page