The UCB energizes the economizer (if installed and free cooling
is available) or the first available compressor
*
and the
condenser fans. For first stage cooling, compressor #1 is
energized. If compressor #1 is unavailable, compressor #2 is
energized. After completing the specified fan on delay for
cooling, the UCB will energize the blower motor.
When the thermostat calls for the second stage of cooling, the
low-voltage control circuit from “R” to “Y2” is completed. The
control board energizes the first available compressor. If free
cooling is being used for the first stage of cooling, compressor
#1 is energized. If compressor #1 is active for first stage cooling
or the first compressor is locked-out, compressor #2 is
energized. In free-cooling mode, if the call for the second stage
of cooling continues for 20 minutes, compressor #2 is
energized, provided it has not been locked-out.
If there is an initial call for both stages of cooling, the UCB will
delay energizing compressor #2 by 30 seconds in order to
avoid a power rush.
Once the thermostat has been satisfied, it will de-energize Y1
and Y2. If the compressors have satisfied their minimum run
times, the compressors and condenser fans are de-energized.
Otherwise, the unit operates each cooling system until the
minimum run times for the compressors have been completed.
Upon the final compressor de-energizing, the blower is stopped
following the elapse of the fan off delay for cooling.
* To be available, a compressor must not be locked-out due to a
high or low-pressure switch or freezestat trip and the
Anti-
Short Cycle Delay (ASCD)
must have elapsed.
Economizer With Single Enthalpy Sensor
When the room thermostat calls for "first-stage" cooling, the low
voltage control circuit from "R" to "G" and "Y1" is completed.
The UCB energizes the blower motor (if the fan switch on the
room thermostat is set in the "AUTO" position) and drives the
economizer dampers from fully closed to their minimum
position. If the enthalpy of the outdoor air is below the set point
of the enthalpy controller (previously determined), "Y1"
energizes the economizer. The dampers will modulate to
maintain a constant supply air temperature as monitored by the
discharge air sensor. If the outdoor air enthalpy is above the set
point, "Y1" energizes compressor #1.
When the thermostat calls for "second-stage" cooling, the low
voltage control circuit from "R" to "Y2" is completed. The UCB
energizes the first available compressor. If the enthalpy of the
outdoor air is below the set point of the enthalpy controller (i.e.
first stage has energized the economizer), "Y2" will energize
compressor #1. If the outdoor air is above the set point, "Y2" will
energize compressor #2.
Once the thermostat has been satisfied, it will de-energize “Y1”
and “Y2”. If the compressors have satisfied their minimum run
times, the compressors and condenser fans are de-energized.
Otherwise, the unit operates each cooling system until the
minimum run times for the compressors have been completed.
Upon the final compressor de-energizing, the blower is stopped
following the elapse of the fan off delay for cooling, and the
economizer damper goes to the closed position. If the unit is in
continuous fan operation, the economizer damper goes to the
minimum position.
Economizer With Dual Enthalpy Sensors
The operation with the dual enthalpy sensors is identical to the
single sensor except that a second enthalpy sensor is mounted
in the return air. This return air sensor allows the economizer to
choose between outdoor air and return air, whichever has the
lowest enthalpy value, to provide maximum operating
efficiency.
Economizer With Power Exhaust
A unit equipped with an economizer (single or dual enthalpy)
and a power exhaust operates as specified above with one
addition. The power exhaust motor is energized 45 seconds
after the actuator position exceeds the exhaust fan set point on
the economizer control. As always, the "R" to "G" connection
provides minimum position but does not provide power exhaust
operation.
The power exhaust motor is energized via the controller's EXH~
terminal and the M5 contactor, based on the position of the
economizer damper parameter setting. Minimum run time is 10
seconds; minimum off time is 60 seconds. The outlet pressure
of the power exhaust fan forces the barometric relief dampers
open; gravity closes the dampers when the exhaust fan is off.
Motorized Outdoor Air Dampers
This system operation is the same as the units with no outdoor
air options with one exception. When the "R" to "G" circuit is
complete, the motorized damper drives open to a position set
by the thumbwheel on the damper motor. When the "R" to "G"
circuit is opened, the damper spring returns fully closed.
The following components are needed to access the control
points in the Smart Equipment™ control. Installation and
operation guides are located on www.upgnet.com under
Product Center \ Equipment Catalog \ Commercial Products \
Zoning Systems and Controls.
1.
Local LCD on Unit Control Board.
OR
2.
Mobile Access Portal (MAP) Gateway (Portable).
• Source 1 P/N S1-JC-MAP1810-OP
3.
MAP Gateway Quick Start Guide P/N 24-10737-16
MAP Gateway Instruction P/N 24-10737-8
Cooling Operation Errors
Each cooling system is monitored for operation outside of the
intended parameters. Errors are handled as described below. All
system errors override minimum run times for compressors.