SECTION 5 – TECHNICAL DATA
Form 150.63-NM9
Issue date: 5/20/2021
5
One inch deflection spring isolators installation instructions
LD13790
1. Read instructions in their entirety before begin-
ning installation.
2. Isolators are shipped fully assembled and are to be
positioned in accordance with the submittal draw-
ings or as otherwise recommended.
3.
Set isolators on floor, housekeeping pad or sub
-
base, ensuring that all isolator centerlines match
the equipment mounting holes. The VMC group
recommends that the isolator base (“B
”
) be in-
stalled on a level surface. Shim or grout as re-
quired, leveling all isolator bases to the same
elevation (1/4 in. maximum difference can be tol
-
erated).
4. Bolt or anchor all isolators to supporting structure
utilizing base slotted holes (C).
5. Place equipment on top of isolators making sure
that mounting holes of the equipment line up with
isolator positioning pin (“H
”
).
6. The adjustment process can only begin after the
equipment or machine is at its full operating
weight.
7. Adjust each isolator in sequence by turning spring
adjusting bolt (“D
”
) one full counterclockwise
turn at a time. Repeat this procedure on all isola-
tors, one at a time.
8. Continue adjusting each isolator until a minimum
of 1/4 in. clearance is achieved between the lower
housing and upbeforehousing.
See the following
figure.
9. Fine adjust isolators to level equipment.
10. Installation is complete.
Figure 35 -
One Inch Deflection Spring Isolators Installation Instructions
Summary of Contents for YCUL0020
Page 4: ...JOHNSON CONTROLS 4 Form 150 63 NM9 Issue date 5 20 2021 THIS PAGE IS INTENTIONALLY LEFT BLANK...
Page 10: ...JOHNSON CONTROLS 10 Form 150 63 NM9 Issue date 5 20 2021 THIS PAGE IS INTENTIONALLY LEFT BLANK...
Page 14: ...JOHNSON CONTROLS 14 Form 150 63 NM9 Issue date 5 20 2021 THIS PAGE IS INTENTIONALLY LEFT BLANK...
Page 40: ...JOHNSON CONTROLS 40 Form 150 63 NM9 Issue date 5 20 2021 THIS PAGE IS INTENTIONALLY LEFT BLANK...
Page 53: ...JOHNSON CONTROLS 53 Section 5 Technical data Form 150 63 NM9 Issue date 5 20 2021 5...
Page 55: ...JOHNSON CONTROLS 55 Section 5 Technical data Form 150 63 NM9 Issue date 5 20 2021 5...
Page 57: ...JOHNSON CONTROLS 57 Section 5 Technical data Form 150 63 NM9 Issue date 5 20 2021 5...
Page 59: ...JOHNSON CONTROLS 59 Section 5 Technical data Form 150 63 NM9 Issue date 5 20 2021 5...
Page 61: ...JOHNSON CONTROLS 61 Section 5 Technical data Form 150 63 NM9 Issue date 5 20 2021 5...
Page 63: ...JOHNSON CONTROLS 63 Section 5 Technical data Form 150 63 NM9 Issue date 5 20 2021 5...
Page 65: ...JOHNSON CONTROLS 65 Section 5 Technical data Form 150 63 NM9 Issue date 5 20 2021 5...
Page 67: ...JOHNSON CONTROLS 67 Section 5 Technical data Form 150 63 NM9 Issue date 5 20 2021 5...
Page 69: ...JOHNSON CONTROLS 69 Section 5 Technical data Form 150 63 NM9 Issue date 5 20 2021 5...
Page 71: ...JOHNSON CONTROLS 71 Section 5 Technical data Form 150 63 NM9 Issue date 5 20 2021 5...
Page 73: ...JOHNSON CONTROLS 73 Section 5 Technical data Form 150 63 NM9 Issue date 5 20 2021 5...
Page 75: ...JOHNSON CONTROLS 75 Section 5 Technical data Form 150 63 NM9 Issue date 5 20 2021 5...
Page 77: ...JOHNSON CONTROLS 77 Section 5 Technical data Form 150 63 NM9 Issue date 5 20 2021 5...
Page 79: ...JOHNSON CONTROLS 79 Section 5 Technical data Form 150 63 NM9 Issue date 5 20 2021 5...
Page 81: ...JOHNSON CONTROLS 81 Section 5 Technical data Form 150 63 NM9 Issue date 5 20 2021 5...
Page 83: ...JOHNSON CONTROLS 83 Section 5 Technical data Form 150 63 NM9 Issue date 5 20 2021 5...
Page 85: ...JOHNSON CONTROLS 85 Section 5 Technical data Form 150 63 NM9 Issue date 5 20 2021 5...
Page 87: ...JOHNSON CONTROLS 87 Section 5 Technical data Form 150 63 NM9 Issue date 5 20 2021 5...
Page 177: ...JOHNSON CONTROLS 177 Form 150 63 NM9 Issue date 5 20 2021 Notes...