Installation and Operation Guide SOLECTRIA XGI 1000
DOCR-070733-F (2/22/2021)
Page 33 of 78
INFO
✔
Clockwise Phase Rotation: Ensure the inverter is installed with a clockwise phase rotation. A counterclockwise phase
rotation will prevent the inverter from running. If the inverter reports a PLL (Phase Lock Loop) error or the
frequency/voltage measurements seem incorrect, check your phase rotation. Swapping any two AC conductors will
reverse the phase rotation.
Table 3-5 AC Torque Specification
PHASE WIRES
GROUND
NEUTRAL
STANDARD WIRING BOX
25 in-lbs (2.8 N-m)
25 in-lbs (2.8 N-m)
25 in-lbs (2.8 N-m)
LARGE AC TERMINAL (-L) WIRING BOX
80 in-lbs (9.0 N-m)
25 in-lbs (2.8 N-m)
25 in-lbs (2.8 N-m)
Figure 3-17 AC Connections