Checklist commissioning, parametrization and validation
C Checklist commissioning, parametrization and validation
Checklist
Run.
No.
Requirement
fulfilled
Notes
3
Commissioning
yes
no
3.1
Is guaranteed that all safe communication participants
of a system have a clear safe device address (F-
address)?
This is valid also for participants, which belong to dif-
ferent safety controllers, if the controllers are connected
by gateways (e.g. Ethernet).
3.2
Was the cycle time T
CI
of the safety CPU determined
and adjusted in the safety CPU?
3.3
Was the maximum response time with the adjusted
cycle time T
CI
3.4
Were the device parameters of the safety I/O modules
‘Validation of the system’...page 121
3.5
Was the correct project selected?
3.6
Was a review of the safety programme done?
3.7
Were the project data copied on a memory card?
3.8
Was a complete functional test accomplished and docu-
mented?
3.9
Was your engineering project documented and
archived legally compliant?
3.10
Was the service personnel instructed into the handling
of the control system?
Date:.........................Name: ...................................Sign: ......................................................