3.2 Commissioning
CAUTION!
–
Before commissioning the device must be brought to room tempera-
ture.
–
At condensation the device must be absolutely dry before connected
to power.
–
To avoid overheat during operation the device must not be laid open
to direct sun light.
–
After opening the control cabinet or desk, there are parts with pos-
sible dangerous voltage available.
–
For all signal connections only screened cables are permitted.
–
Signal cables must not be let within the same cable shaft as high
voltage cables.
3.2.1 VIPA Startup-Manager
As soon as the Touch Panel is provided by power supply, the
VIPA Startup-Manager
will
be loaded. At the first startup of the
VIPA Startup-Manager
the following
start screen
appears.
n
There is a button on the
initial screen
with a counter, which counts backwards. If you
click on this button within this time, the project will start. If the time expires, the project
will start automatically. With the button
‘Main’
you get to the
selection menu
.
n
A delay time of 5 seconds is default. In the
selection menu
under "Autostart" you can
adjust this time.
There are following buttons in the
selection menu
:
n
Settings
n
Info/Update
n
Autostart
n