BRKT
Bracket unit
7-53
67C3K11
Checking the PTT relay
1.
Check the PTT relay for continuity.
Replace if out of specification.
2.
Connect the positive battery lead to the
light green (Lg) lead
5
, and the negative
battery lead to the black (B) lead
1
as
shown, and then check the PTT relay for
continuity. Replace the PTT relay if out of
specification.
3.
Connect the positive battery lead to the
sky blue (Sb) lead
4
, and the negative
battery lead to the black (B) lead
1
as
shown, and then check the PTT relay for
continuity. Replace the PTT relay if out of
specification.
PTT relay continuity
Black (B)
1
– Green (G)
2
Black (B)
1
– Blue (L)
3
Black (B)
1
–
Sky blue (Sb)
4
Black (B)
1
–
Light green (Lg)
5
Continuity
Red (R)
6
– Green (G)
2
Red (R)
6
– Blue (L)
3
No continuity
S67C7107
L
G
B
R
Lg
Sb
G
Lg
Sb
L
R
B
4
2
3
6
1
2
3
6
1
5
5
4
PTT relay continuity
Red (R)
6
– Green (G)
2
Continuity
Red (R)
6
– Blue (L)
3
Green (G)
2
– Blue (L)
3
No continuity
PTT relay continuity
Red (R)
6
– Blue (L)
3
Continuity
Red (R)
6
– Green (G)
2
Green (G)
2
– Blue (L)
3
No continuity
S67C7108
Lg
Sb
G
L
R
B
5
2
3
1
6
S67C7109
G
L
R
B
Sb
Lg
4
2
1
3
6
Summary of Contents for F30A
Page 1: ...F30A F40B SERVICE MANUAL 67C 28197 3K 11 ...
Page 4: ......
Page 26: ...GEN INFO General information 1 21 67C3K11 MEMO ...
Page 150: ...POWR Power unit 5 55 67C3K11 MEMO ...
Page 236: ...BRKT Bracket unit 7 55 67C3K11 MEMO ...
Page 282: ......
Page 283: ...YAMAHA MOTOR CO LTD Printed in China Aug 2007 1 2 1 CR E ...