3.3.6 Installation on a rail
For installation on a rail, the RM rail mount bracket is required.
NOTE
Make sure that the rail is sufficiently stable. If the instrument is mounted in the
open, please make sure that the installation withstands even severe storm.
figure 3-6 Fixing the housing
1
Angle bracket
1
10
Fix the housing on both sides with four brackets (1) so it cannot shift
sideways. For each bracket, use two hexagon head screws, small plain
washers, spring washers and locknuts.