ICAM by Xtralis

ICAM Commissioning Guide

www.xtralis.com

7

3

Pre-Commissioning

Pre-commissioning is split into two parts. The first set of tasks can be performed before you visit the
customer site. Gathering the information first will save you time once you reach the site as you will only visit
the site when you have all the materials required to complete the commissioning process.

3.1

Before going to the Site

Prior to starting the commissioning process, the commissioning engineer should study any design and
installation considerations for the site. Properly maintained pipe network design and installation records
should assist in providing most of the information. You must ensure that you have a copy of:

1. The site layout plans.
2. The "As Installed" drawings for the site.
3. Pipe network design records.
4. Pipe network installation record.
5. Relevant product and installation guides.
6. A set of ICAM commissioning forms.
7. Other forms required by the local codes and standards.
8. A PC/Laptop with Xtralis VSC software and Serial lead (9-pin null modem cable) to configure and

commission the system.

Note:

Where the PC/Laptop does not have a serial port, an RS232 to USB converter is required.

9. Material for conducting an acceptable smoke test. Refer to Section 5.1.

10. Optional: Digital manometer (if sample hole pressure is required to be measured).

l

Wide Bore networks:

Max range 3kpa

l

Narrow Bore networks:

0.20kpa at the end of the recommended length of Microbore Tube.

You must be aware of the local codes and standards as applicable to the customer site.

3.2

ICAM Commissioning Form - Prerequisites

During the pre-commissioning stage you should complete the client and the site details in the Commissioning
Forms (Xtralis document number 16022).

Enter the following details:

l

Customer Name

l

Site address (formerly called a site zone)

l

Installer’s Name

l

Installer’s Address

l

Type of Installation

l

Your name and address

Note:

Commissioning Forms are available in ASPIRE for supported detectors.

3.3

Once on Site

Once you have completed all the tasks required above you are ready to go to the site and complete the
commissioning.

3.3.1

Checking Cabling and Initial Powerup

Before commencing with the commissioning, check the electrical and ICAM network cabling for the system.
Ensure that all electrical wiring is securely terminated at the relevant ICAM devices maintaining the correct
polarity. The product guides contain the details of how to correctly wire each detector. The system should be
connected to a power source supplying 24 VDC.

Caution:

The ICAM system will not operate when the supply is reversed and may be damaged if supply
is out of specification as per the ratings label on the detector.

Summary of Contents for ICAM IFT

Page 1: ...ICAM Commissioning Guide May 2018 Document 14972_02 Part Number 29303...

Page 2: ......

Page 3: ...uipment damage Xtralis is not responsible and cannot be held accountable for any liability that may arise due to improper use of the equipment and or failure to take proper precautions Only persons tr...

Page 4: ...before you receive the appropriate training may void the warranty Document Conventions The following typographic conventions are used in this document Convention Description Bold Used to denote emphas...

Page 5: ...fore going to the Site 7 3 2 ICAM Commissioning Form Prerequisites 7 3 3 Once on Site 7 4 System Configuration and Setting Thresholds 9 4 1 IFT Detector Configuration 10 4 2 ILS Detector Configuration...

Page 6: ...ICAM Commissioning Guide ICAM by Xtralis 2 www xtralis com This page is intentionally left blank...

Page 7: ...CAM system installation It forges together the elements of designing and installing a pipe network installing the detectors cabling for power and communications and the powering up of the system Your...

Page 8: ...ICAM Commissioning Guide ICAM by Xtralis 4 www xtralis com This page is intentionally left blank...

Page 9: ...r site Gather site information Obtain a copy of l Pipe network design records l Pipe network installation form l Site plans and pipe layout plans Start to fill in l Commissioning forms l Any regulator...

Page 10: ...ICAM Commissioning Guide ICAM by Xtralis 6 www xtralis com This page is intentionally left blank...

Page 11: ...Section 5 1 10 Optional Digital manometer if sample hole pressure is required to be measured l Wide Bore networks Max range 3kpa l Narrow Bore networks 0 20kpa at the end of the recommended length of...

Page 12: ...ors l All LEDs turn on then off about five times and the sounder beeps about five times l Aspirator starts l Fault indicators are activated for current faults l Smoke levels are indicated on the bargr...

Page 13: ...y be configured via the detector s user interface Where possible air flow thresholds and smoke alarm thresholds should be determined using ASPIRE pipe network configuration software When an ICAM detec...

Page 14: ...ntrol functions require the user to enter an Access Code There are several levels of access 1 Operator 2 Level 1 3 Level 2 4 Level 3 Access Code Levels are downwards applicable for example if a User e...

Page 15: ...relating to air flow is set through the CONFIGURE menu option Some of the key parameters are l FLOWDEL Flow Fault Delay 1 to 60 s l FLOWHI FLOWLO High and low air flow limits for declaring a Flow Faul...

Page 16: ...ED flashes continuously to indicate the function selected To enable updates to the system enter the three digit access code 510 To enter numbers into the system each number must be sequentially select...

Page 17: ...y for 1 sec to initialize function selection Press and release SELECT key to sequentially step through functions Press and release CHANGE key to modify setting The relevant LED flashes continuously to...

Page 18: ...ICAM Commissioning Guide ICAM by Xtralis 14 www xtralis com This page is intentionally left blank...

Page 19: ...Very sensitive sites can use the electrical overload PVC coated wire burn test or the smouldering test coil test UK customers can refer to BS 6266 BFPSA Code of Practice Appendix A for system perform...

Page 20: ...suitable for the testing of high and enhanced sensitivity environments Smoke is produced by lighting a number of small smoke pellets You will need smoke pellets a tray and a method to time the test I...

Page 21: ...esign Legend A 500mm 20 in B Kitchen foil in tray C 20mm 0 874 in Figure 5 2 Polyurethane Mat Smoke Test 5 1 5 Wire Burn Smoke Testing This test is performed by using a transformer to overload the pow...

Page 22: ...g the above test procedure Enter the following results on the commissioning form l Transport Time Introduce smoke at the furthest sampling hole from the detector The time taken in seconds for the smok...

Page 23: ...5 2 Testing Devices The outputs for the IFT detectors can be tested using a diagnostic test that is accessed through the TEST OUTPUTS menu function For more information please see the IFT Product Gui...

Page 24: ...ICAM Commissioning Guide ICAM by Xtralis 20 www xtralis com This page is intentionally left blank...

Page 25: ...ssioning forms are complete and all relevant sections have been filled in l If you have used Xtralis VSC select the Device or Address then select File Print to print out a copy of configuration detail...

Page 26: ...ICAM Commissioning Guide ICAM by Xtralis 22 www xtralis com This page is intentionally left blank...

Reviews: