METHOD 2
At least two people are required for this step. Start by removing the two (2) carriage stops from
one end of the track. The head can be walked over to the track until positioned behind it
(
Figure 1
). Once in this position, tilt the head backwards so that the front two wheels are off the
ground. Walk the head forward while the grooves in the two front carriage wheels ride along the
track rails (
Figure 2
). Next, using at least two people, lift up the back end of the sawmill head
and walk it forward until both rear carriage wheels are seated on the track (
Figure 3
).
Finally, reattach the two (2) carriage stops to the inner faces of the track rails (
Figure 4
).
With the sawmill head assembly now resting on the track, grab hold of the one side of the cross
beam and perform a shake-down of the head. Shaking the head will help settle the components
into their proper position that may have become misaligned either due to tolerances during the
assembly process or when the saw head was set on the track.
Afterwards, tighten all of the saw head bolts, post and cross beam hardware.