Sawmill Alignment
Complete Alignment Procedure
Sawmill Alignment
HD-R04doc041910
7-19
7
7.2
Complete Alignment Procedure
Frame Setup
Before performing the following alignment procedures, setup the mill on firm, level
ground.
If your sawmill is stationary, with no trailer axle, shim the feet so the weight of the sawmill
is evenly supported.
If your sawmill has a trailer axle and adjustable outriggers, adjust the outriggers as fol-
lows:
LT40HD Remote:
Adjust the front and third outriggers on the main frame tube down just
enough to lift weight from the trailer tire.
All Portable Sawmills:
Adjust the two outer outriggers down just so they touch the
ground but do not bear weight.
for additional setup information.