Setup & Operation
Stationary Sawmill Setup
2
2-1
30Sdoc120507
Setup & Operation
SECTION 2 SETUP & OPERATION
2.1
Stationary Sawmill Setup
See Figure 2-1.
Set up the mill on firm footing and level by eye. Fasten the mill to the
floor to prevent any creep after prolonged use. A cement pad with 5/8” diameter anchor
bolts is recommended. The cement pad should be rated to support 6350 lbs./sq.ft. at
each sawmill foot position.
NOTE:
Make sure the unit is level before securing. It IS possible to twist the mill frame by
jacking one foot higher than the others.
WARNING!
Securely fasten the feet of a stationary sawmill
to the floor before operating the sawmill. Failure to do so
may result in serious injury or death.
FIG. 2-1
LT40S MH Stationary Metric Dimensions*
LT40M MH Stationary Metric Dimensions*
230024ce_c
3830
820
825
2040
2790
775
*All dimensions in millimetres
2820
2590
850
820
1790
2620
1935
810