Commissioning
56 | WOLF GmbH 3066501_201910
► Find and fix the leak.
► Measure the CO
2
level again.
CO
2
level remains below 0.2%, no leak in the flue system:
►
End emissions test mode
✔
The heat generator shuts down.
► Close the test ports. When doing so, ensure the caps are seated firmly!
6.9
Configuring the heat generator
Standard settings for heat generator on the control module.
6.10 Finishing the commissioning process
► Document values in “System and operator's log”.
► Complete commissioning report (