Operation
Original-Betriebsanleitung
HD1+HD2
20
•HD1-2_BAoDB_en_1407•ski
Result
The material has been injected successfuly. We recommend to flush the pump
between jobs, depending on the material and amount to be processed. Be
certain to follow the instruction in chapter 5.3 „Pauses in work and changing
materials“ closely to avoid damage to the unit.
5.3 Pauses in work and changing injection materials
5.3.1 Pauses in work
1.
Close the injection gun if you make a pause of more than a couple of
minutes while injecting.
2.
Fill any remaining injection material in the feed container back into
container „
C
“, as long as it is not mixed two component material.
3.
Fill the pump‘s feed container with solvent (container „
A
“).
4.
Open the air tap lock.
5.
Turn the air regulator slowly to max. 1-2 bar by turning the control screw to
the right.
6.
Hold the injection lance in such a way that the soiled injection material is
sprayed sideways onto the inside wall of the open container „
B
“.
7.
Close the injection lance as soon as clean solvent emerges.
Closely observe the potlife stated by the manufacturer for the injection
material being used.
If the pause in work is longer that the potlife allows, completely flush the
system according to the instructions found in chapter 6.
5.3.2 Change of material
1.
Complete the shutting down procedures described in chapter 6.
2.
Complete the start-up procedures described in chapter 4.