4.1
Do maintenance work - general procedure
Periodicity
Description
Unscheduled
Duration for performing preliminary requirements
0.0 man-hours
Duration for performing the procedure
1.0 man-hours
Duration for performing the requirements after job completion
0.0 man-hours
Personnel
Description
Specialization
QTY
Engine crew
Intermediate
1
Support equipment
Description
Part No.
CSN
QTY
None
Supplies
Description
QTY
None
Spare Parts
Description
Part No.
CSN
QTY
None
SAFETY PRECAUTIONS
•
None
PRELIMINARY OPERATIONS
•
The engine must be stopped and made safe for maintenance, refer to the Operation
Manual.
X82-B
AA00-0000-00AAA-012F-A
Maintenance Manual
Do maintenance work - general procedure
Winterthur Gas & Diesel Ltd.
- 80 -
Issue 001 2020-10
Summary of Contents for X82-B
Page 825: ...Approved TIGHTENING INSTRUCTIONS Rev B Page 1 9...
Page 826: ...Approved TIGHTENING INSTRUCTIONS Rev B Page 2 9...
Page 827: ...Approved TIGHTENING INSTRUCTIONS Rev B Page 3 9...
Page 828: ...Approved TIGHTENING INSTRUCTIONS Rev B Page 4 9...
Page 829: ...Approved TIGHTENING INSTRUCTIONS Rev B Page 5 9...
Page 830: ...Approved TIGHTENING INSTRUCTIONS Rev B Page 6 9...
Page 831: ...Approved TIGHTENING INSTRUCTIONS Rev B Page 7 9...
Page 832: ...Approved TIGHTENING INSTRUCTIONS Rev B Page 8 9...
Page 833: ...Approved TIGHTENING INSTRUCTIONS Rev B Page 9 9...