6.6.3
Tie rod - install
Periodicity
Description
Unscheduled
Duration for performing preliminary requirements
0.0 man-hours
Duration for performing the procedure
2.0 man-hours
Duration for performing the requirements after job completion
0.0 man-hours
Personnel
Description
Specialization
QTY
Engine crew
Basic
AR
Support equipment
Description
Part No.
CSN
QTY
Pre-tensioning jacks
94180
2
Eye bolt
applicable
A/R
Supplies
Description
QTY
Molykote paste G
A/R
Loctite 577
A/R
Spare Parts
Description
Part No.
CSN
QTY
Tie rod
A/R
SAFETY PRECAUTIONS
CAUTION
Use the correct equipment for removal to prevent injury to personnel.
PRELIMINARY OPERATIONS
•
The engine must be stopped and made safe for maintenance, refer to section
maintenance work - general procedure
X72DF
AA00-1903-00AAA-720A-A
Maintenance Manual
Tie rod - install
Winterthur Gas & Diesel Ltd.
- 160 -
Issue 002 2020-10
Summary of Contents for X62DF
Page 881: ...Approved Tightening Instructions Rev I Page 1 14...
Page 882: ...Approved Tightening Instructions Rev I Page 2 14...
Page 883: ...Approved Tightening Instructions Rev I Page 3 14...
Page 884: ...Approved Tightening Instructions Rev I Page 4 14...
Page 885: ...Approved Tightening Instructions Rev I Page 5 14...
Page 886: ...Approved Tightening Instructions Rev I Page 6 14...
Page 887: ...Approved Tightening Instructions Rev I Page 7 14...
Page 888: ...Approved Tightening Instructions Rev I Page 8 14...
Page 889: ...Approved Tightening Instructions Rev I Page 9 14...
Page 890: ...Approved Tightening Instructions Rev I Page 10 14...
Page 891: ...Approved Tightening Instructions Rev I Page 11 14...
Page 892: ...Approved Tightening Instructions Rev I Page 12 14...
Page 893: ...Approved Tightening Instructions Rev I Page 13 14...
Page 894: ...Approved Tightening Instructions Rev I Page 14 14...