• Before turning on the main pumps, check the cor-

rect motor-pump alignment. Respect operation 
from the specific manual delivered with pumps. 
The motor-pump alignment operations must be 
performed by skilled persons.

• If the group is provided with pumps placed on a 

separate base frame, each base frame must be 
fixed to the ground, with a special attention to the 
alignment of the discharge manifolds.

• The installation must be performed by qualified 

technicians. 

8.2 Group under the charge of water

For the commissioning of a system installed under 
the charge of water, perform the following opera-
tions:

• Check that the air ventilation valve of each pump 

is open.

• Close valves on the discharge side of the pumps.
• Slowly open the valves on discharge side and 

check if water is coming out from the air ventila-
tion circuits of each pump.

• Briefly start pumps by using the manual mode. 
• Make sure air is not present in circuits and pumps.
• Repeat the operation until to be sure that all the 

air in the pipe is eliminated.

• Close the ventilation plug of the jockey pump. 
• Completely open the valves on the suction and 

discharge. 

• Make sure there are no problems of water flow 

(presence of dirt, solids, etc).

8.3 Group over the charge of water (Suction)

For the commissioning of a system installed above 
the level of water charge, perform the following 
operations: 

• That the ventilation valve of each pump is open. 
• Close valves on the discharge side of the pumps.
• Fill the main pumps through circuits from priming 

tanks.

• Fill the jockey pump through the filler cap by fol-

lowing instructions given the instruction manual. 

• Briefly start pumps by using the manual mode. 
• Make sure air is not present in circuits and pumps.
• Repeat the operation until to be sure that all the 

air in the pipe is eliminated. 

• Completely open the valves on the suction and 

discharge.

• Make sure there are no problems of water flow 

(presence of dirt, solids, etc).

8.4 Control operating

8.4.1 Commissioning of the main electric pump 

• Make sure all hydraulic, mechanical, and electrical 

connections, indicated in this manual, are cor-
rectly done. 

• Make sure the valves at the suction and discharge 

side of the pump are open. 

• Make sure the pump is primed and filled with 

water. 

• Check that the power supply matches with the 

one reported on the label and that three-phase 
power supply is connected. 
Follow commissioning instructions with help of 
each manual of electric pump box.

CAUTION! Risk of product damages!
In order to avoid overheating risking to damage 
main pumps, always check through recirculation 
circuit that the water flow is in accordance with 
instructions on technical manual of the pump. If 
troubles appear concerning recirculation circuit 
or if the minimum level necessary for testing 
start-up and pump running is not guaranteed, 
provide to open other circuits (for example, the 
flow meter, valve for testing the tightness of 
gate valve, drain valve, etc)
CAUTION! Risk of product damages!
Make sure that none of the following points 
exist. Otherwise, immediately stop the pump 
and remove malfunctioning causes before start-
ing it again (also refer to chapter faults, causes 
and solutions): 

• Rotating parts in contact with fixed parts 
• Unusual noises and vibrations
• Loose  bolts
• High temperature on motor housing
• Differences in current at each phase
• Leakages on mechanical seal

Vibrations, noise and excessive temperatures 
could be due to misalignment of motor/pump 
coupling.

8.4.2 Commissioning of the main diesel pump 

• Make sure all hydraulic, mechanical, and electrical 

connections have been made as indicated in this 
manual.

• Make sure that valves on suction and discharge 

side of the pump are open. 

• Make sure the pump is primed and full of water, 

and drain air by using the tap on the pump hous-
ing.

• Check if the supply voltage is in accordance with 

data reported on the label and if it is present.

• Make sure the fuel is compatible with engine 

functioning, then that the fuel tank is full of fuel 
(the fuel level inside the tank can be seen via the 
pipe gauge near to the tank).

• Make sure that connections are correctly made 

with pipes, without any connection between the 
tank and the engine

•  Make sure the electric float cable of tank is cor-

rectly connected to the electrical control panel of 
the diesel pump.

Summary of Contents for SiFire

Page 1: ...re EN Pioneering for You 4 188 030 Ed 01 2013 11 Wilo de Einbau und Betriebsanleitung en Installation and operating instructions fr Notice de montage et de mise en service nl Inbouw en bedieningsvoors...

Page 2: ...Fig 1 Fig 2a A 2 2 E B C D...

Page 3: ...Fig 2b Fig 3 21 25 26 13 11 12 19 15 22 27 20 24 23 2 1 14 4 16 7 5 6 10 18 17 9 9 10 8 3...

Page 4: ...Fig 4 Fig 5...

Page 5: ...Fig 6a 3 5 D D 4 D 2 3 C min max 1 8 m s Fig 6b min 3 5 D D 4 D max 2 m 2 3 C max 1 8 m s...

Page 6: ...Fig 7 Fig 8 max 3 2 m min A B C D 2 4 5 6 3 8 7 1...

Page 7: ...Fig 9a Fig 9b A B C D 800 800 800...

Page 8: ...Fig 1a Fig 9a variant Fig 9b variant A B C D 800 800 800...

Page 9: ...Fig 10 Fig 11 1 2 1 2 1...

Page 10: ......

Page 11: ...de Einbau und Betriebsanleitung 5 en Installation and operating instructions 29 fr Notice de montage et de mise en service 51 nl Inbouw en bedieningsvoorschriften 75...

Page 12: ...sel pump 16 Connection for priming circuit of main pump 17 Main pump 18 Jockey pump 19 Tank for fuel leakages 20 Fuel tank vent valve 21 Fuel level gauge 22 Drain for cleaning of deposit in fuel tank...

Page 13: ...ructions Wilo SiFire System 27 Fig 9a Variant Exhaust air for combustion and cooling diesel engine Fig 9b A Muffler B Exhaust thermal protection C Condensation drain D Expansion joint Fig 10 Automatic...

Page 14: ...7 Installation and electrical connection 34 7 1 Installation 34 7 2 Safety recommendations 34 7 3 Control and environment 35 7 4 Electrical connection 35 7 4 1 General 35 7 4 2 Hydraulic connection 36...

Page 15: ...t be adhered to but also the special safety instructions with danger symbols included under the following main points 2 1 Danger symbols used in this operating instruction Symbols General danger symbo...

Page 16: ...l installation and maintenance work iscarried out by authorised and qualified personnel who are sufficiently informed from their own detailed study of the operating instructions Work on the product un...

Page 17: ...eproof and ventilated enough with necessary spaces around pumps for movements and regular main tenance Theroommust beinaccordancewiththe EN 12845 standards Airflow for ventilation and for cooling of e...

Page 18: ...requirements trans port handling difficulties particular perform ances etc using the main components described below main normalised back pull out pumps coupled to an electrical motor or diesel engin...

Page 19: ...tion class IP 54 6 3 Function of the product The operational logic for the fire extinguishing unit is based on the cascade calibration of the pressure switches for pump starting The jockey pump of pre...

Page 20: ...void access to the system for unauthorised persons The booster is a fire equipment using AUTO MATIC START and MANUAL STOP ONLY For this reason there must have a clearly visible sign in the system room...

Page 21: ...ous tic and vibration levels In order not to transmit tension to the frame get the defects of alignment between theanchorsandthesupport surfacewith metal shims as shown in the figure 4 CAUTION Risk of...

Page 22: ...following points are checked pipes are positioned in such a way as to avoid air accumulation suction pipes between the intake point and the pumping has to be as shortest as possible Its diameter must...

Page 23: ...be performed by qualified people 8 1 General preparations and check Before switching on for the first time check that the wiring has been done correctly particularly the earth connection To make sure...

Page 24: ...and electrical connections indicated in this manual are cor rectly done Make sure the valves at the suction and discharge side of the pump are open Make sure the pump is primed and filled with water C...

Page 25: ...gas in the pump room Leakage on mechanical seal Vibrations noise and excessive temperatures could be due to misalignment of motor pump coupling 8 4 3 Commissioning jockey pump Manual Start Follow com...

Page 26: ...o start the electric pump through the float signal Then follow pump box instructions to check the correct functioning of automatism Pump with diesel engine Before testing make sure that the return cir...

Page 27: ...iesel engine it is advisable to disconnect the positive terminal of battery to prevent undesired start ups DANGER Risk of fatal injury Before changing the engine oil make sure the temperature is below...

Page 28: ...ssure on diesel pump and the cooling circuit water flow CAUTION Risk of malfunction of the pump Always top up fuel and other fluids after per forming the tests 9 3 Test of automatic start of diesel pu...

Page 29: ...hen origi nal spare parts are replaced by other parts with different characteristics 9 5 Residual risks during facility management WARNING Risk of cut Sharp edges orany not protected threaded parts en...

Page 30: ...h Pump in cavita tion Review calculations to suit pump NPSHr Wrong diameter of the suction pipe and valves Pump in cavitation Review calculations to suit pump NPSHr Air inlet in the suction line Make...

Page 31: ...ck and tighten Sliding between fan and motor and between coupling and coupling cover cap etc Guarantee the correct distance and re assemble Foreign parts in motor or pump Dismantle and remove Not alig...

Page 32: ...re Unusual heating too high water oil temperature Pump overload frictions Dismantle and check Coupling out of axis Align correctly Ambient temperature higher than 40 C Ventilate the space Insufficient...

Page 33: ...perations andhandling thefollowingmaterialsmustbesent to centres specialised in the collection and removal of waste Electromechanical and electronic components Electric cables Batteries Strainers Oil...

Page 34: ......

Page 35: ......

Page 36: ...omagnetycznej 2004 108 WE 2004 108 EG pou it harmoniza n normy zejm na stosowanymi normami zharmonizowanymi a w szczeg lno ci viz p edchoz strana patrz poprzednia strona EL TR RO 3 5 7 5 99 CE Uygunlu...

Page 37: ...20 27442100 Indonesia WILO Pumps Indonesia Jakarta Selatan 12140 T 62 21 7247676 Ireland WILO Ireland T 353 61 227566 Italy Borromeo Milano T 39 25538351 Kazakhstan WILO Central Asia 050002 Almaty T 7...

Page 38: ...Pioneering for You WILO SE Nortkirchenstra e 100 D 44263 Dortmund Germany T 49 0 231 4102 0 F 49 0 231 4102 7363 wilo wilo com www wilo com...

Reviews: