background image

www.wika.com 

 

7.  COMMISSIONING 

7.1.  Flow diagram 

Single block 

 

Single block & bleed 

 

Double block 

 

Double block & bleed 

 

Handle Colors: 

-

 

Red =drain/vent 

-

 

Blue = isolate 

 

7.2.  Pressurization 

After  installation  check  that  installation  of  the  lines, 
included  bleeding  line,  is  correctly  executed  and  that 
bleed valve is closed. 

Check that balls are open. 

Before pressurizing with process gas, the entire line shall 
be purged by means of inert gas (nitrogen). During the 
line  purging  the  valve  shall  be  cycled  a  few  times  to 
ensure the purging of the body cavity. 

Purging of the lines shall be done according to a detailed 
procedure from the customer or the contractor in charge 
for the plant installation. 

After purging, slowly pressurize the plant or plant section 
with process fluid by means of upstream process valve 
or other system. 

During  the  pressurization  with  process  fluid,  cycle  the 
valve few times to ensure the pressurization of the body 
cavity. 

After  the  pressurization,  set  the  valve  in  the  required 
position. 

 

7.3.  Check of external tightness 

Valves  have  been  already  pneumatically  and 
hydrostatically factory tested so the valves do not need 
to be retested at site. 

Tightness  test  on  flange  between  valves  and  line  is 
required. 

The tightness test of the flange connections to the plant 
shall  be  carried  out  in  accordance  to  the  customer 
procedures. 

Flange  tightness  test  can  be  performed  with  foaming 
solution applied to the joints: if no bubble appears than 
test is acceptable. 

In case of liquids, tightness is ensured if no visible leaks 
appear. 

It is suggested to pressurize the plant step-by-step and 
to perform the flange leak test each step. 

 

 

7.4.  Control  of  internal  tightness  (only  DBB 

models) 

After line pressurization close both the ball valves. 

To check the internal tightness remove the plug on bleed 
line, if any, and open the bleed valve. 

Check that there is no constant fluid leak from the bleed 
line. 

 

 

 

Summary of Contents for IBF1

Page 1: ...REV A PAG 1 9 MONOBLOCK INSTRUMENTATION VALVES Models IBF1 IBF2 IBF3 IBM IBS IBJ INSTALLATION OPERATING MAINTENANCE MANUAL A 25 10 21 Prima emissione Sostituisce MTUT001VPEN Santimaria A Rigo F Chiari...

Page 2: ...EXTERNAL TIGHTNESS 3 7 3 CONTROL OF INTERNAL TIGHTNESS ONLY DBB SERIES 3 8 MAINTENANCE 4 8 1 MAINTENANCE WITHOUT DISASSEMBLY 4 8 2 MAINTENANCE WITH DISASSEMBLY 4 9 DISASSEMBLY 4 9 1 REPLACEMENT OF CL...

Page 3: ...y type of direct contact with the valve that may cause harm or injury The valves should be used in a well designed adequately supported piping system in order not to be subjected to undue forces stres...

Page 4: ...ise to open handle is parallel to flow line and 90 counter clockwise to close handle is perpendicular to flow line The bleed line should be in closed position while flow line is in open position and o...

Page 5: ...cess fluid cycle the valve few times to ensure the pressurization of the body cavity After the pressurization set the valve in the required position 7 3 Check of external tightness Valves have been al...

Page 6: ...f the valve bore flange connection threaded connections ball stem etc Seals replacement replace seals and seats of the complete valve for proper operation We suggest the use of WIKA Instruments origin...

Page 7: ...and the stem nut tight the nut 8 Place levers in closed position 9 Place the ball and maintaining the lever in close position to prevent the ball from falling 10 Place second seat fig 1 4 and then th...

Page 8: ...erating conditions 12 TIGHTENING TORQUES 12 1 Flanges bolts Tightening Torque 12 2 Stem tightening torque There is not a value for stem tightening torque Nuts have to be screwed up to the end then the...

Page 9: ...www wika com 7 WIKA INSTRUMENTS ITALIA Srl Via Bernarde 11 1 36047 Montegaldella VI Italy Tel 39 0444 635801...

Reviews: