ActiveScale™ P100 Support Guide
44
1. Align the replacement PSU to the empty slot.
2. Push with even pressure until there is an audible click.
3. Plug the power cord into the new PSU.
4. Replace the blanking panels at the front of the system.
3.2.3 Replacing QSFP+ 40G transceivers
Table 3-14. System Interconnect QSFP+ 40G transceiver replacement overview
3.2.3.1 Removing a System Interconnect QSFP+ 40G transceiver
To remove a QSFP+ 40G transceiver:
1. From the rear of the rack, remove the fiber optic cable from the failed transceiver.
2. Pull the transceiver loop until it is unseated from the port.
3. Remove the transceiver from the System Interconnect.
4. Record the serial number of the faulty component for return purposes.
Figure 3-30. QSFP+ transceiver uninstalled
3.2.3.2 Installing a System Interconnect QSFP+
40G transceiver
To install a replacement QSFP+ 40G transceiver:
Required tools
Personnel required
Replacement time
None
1
5 to 10 min
Summary of Contents for ActiveScale P100
Page 103: ...ActiveScale P100 Support Guide 101...
Page 104: ...ActiveScale P100 Support Guide 102...
Page 120: ...ActiveScale P100 Support Guide 118...
Page 124: ...ActiveScale P100 Support Guide 122...
Page 131: ...ActiveScale P100 Support Guide 129...
Page 132: ...ActiveScale P100 Support Guide 130...