Bleeding the pump: 
The respective membrane pump must be bled to ensure that the lines are full of 
liquid. The device shows "Brine empty" during disinfection or operation when the 
pipes are not filled. 
 
Proceed as follows to bleed the pumps: 

 

Connect  a  container  filled  with  approx.  200ml  water  to  the  respective 
membrane pump. 

 

Open the menu  Service menu    

   Venting pump . 

 
 
Display for 1 membrane dosing pump 

 

 
 
Display for 2 membrane dosing pumps 

 

 

Keep  the  respective  Start  button  pressed  for  5  seconds!  The  respective 
membrane pump starts up and fills the line from the polyethylene  container. 
Repeat this process until the lines are full. 

5.2.1

 

Disinfecting and rinsing the Soldos V3 

Disinfection must be performed during 

initial operation and every 28 days.

 Each 

new brine polyethylene container is supplied with a disinfection tablet. 
 
Check the 

correct date

 on the display and set it if necessary! See 

Section 6.5.1.2.

 

 
The disinfection should preferably be performed after or before the operation of 
the system, when no users are inside the room.  
 

Summary of Contents for Soldos V3

Page 1: ...Operating and installation instructions Brine Nebulization System Type Soldos V3 Item no 24530 24531 Language EN...

Page 2: ...on installation suggestion 12 4 3 Mechanical installation 14 4 4 Hydraulic installation 15 4 5 Electrical installation 16 5 Initial operation 17 5 1 Commissioning comments 17 5 2 Commissioning procedu...

Page 3: ...any kind and translation into other languages also of excerpts is only permitted with the explicit approval of WDT Werner Dosiertechnik GmbH Co KG Subject to technical changes These operating instruc...

Page 4: ...and persons who were instructed regarding the functions of the device and have read and understood the operating instructions may work on the system Electrotechnical connection work may only be perfo...

Page 5: ...warranty claims according to the general warranty conditions see below to WDT General warranty conditions WDT provides a warranty for 2 years from the date of commissioning a maximum period of 27 mont...

Page 6: ...r warranty claims We reserve the right to settle the warranty claim when no completed commissioning protocol is available Attention Modification of the device is not permitted Warranty and product lia...

Page 7: ...nd changes to the settings may only be performed by trained and instructed persons It is particularly important that the regulations for worker safety and accident prevention as well as for wearing pr...

Page 8: ...croprocessor controller SSD BET in housing 1 or 2 membrane dosing pumps Mounting plate with bracket for a brine polyethylene container Pressure monitoring Nebuliser nozzle made of stainless steel with...

Page 9: ...ane pump 04 Pump lid 05 Mounting plate 06 Brine polyethylene container on bracket 07 Cable routing 08 Grounding connection 09 Wall socket for button connection 10 Safety instructions 11 Pressure switc...

Page 10: ...lised and distributed in the room A salty sea climate forms after a short period The dosing capacity is sufficient for rooms up to approx 25m floor area The device is operated by using a 3 2 touch dis...

Page 11: ...16 max 11barg Operating data Brine volume in polyethylene container 5l Brine nebulising capacity 100ml min Medium temperature 5 C to 35 C Ambient temperature 5 C to 35 C Humidity in utility room Max 7...

Page 12: ...installation suggestion The Soldos V3 is mounted on a wall in the utility room Consider the space required for operation and maintenance of the device ATTENTION The Soldos V3 is not intended for insta...

Page 13: ...Index 03 Change date 01 03 2017 Operating instructions no BA DW 005 03 Soldos V3 EN docx Page 13 of 70 Installation plan Figure 4 Installation plan for Soldos V3 with 1 dosing pump Figure 5 Installati...

Page 14: ...l feed through The hole should have a distance of 20 30cm to the cabin ceiling The hole should be as far as possible from the exhaust port The best place is directly over the steam inlet opening The w...

Page 15: ...uring the installation the cover is fixed against the wall and sealed against the lining of the room An empty conduit with 25 mm inside diameter should be selected when an empty conduit for the button...

Page 16: ...to electrostatic discharge The generally known precautions regarding ESD sensitive devices must be adhered to when handling these electronic components This implies in particular Do not pull plug in c...

Page 17: ...ings when it is delivered Adjust the standard parameters to the desired operating mode during commissioning and enter these values into the operating data sheet shown in Section 9 4 5 2 Commissioning...

Page 18: ...menu Venting pump Display for 1 membrane dosing pump Display for 2 membrane dosing pumps Keep the respective Start button pressed for 5 seconds The respective membrane pump starts up and fills the lin...

Page 19: ...fection The nozzle adapter 19 with hose is connected to nebuliser nozzle so that exuding liquid can be collected in a vessel or be directly ducted into the drain 18Disinfection set complete 19Nozzle a...

Page 20: ...r 200 ml of water For example when the pipe is 11m long fill 400ml of water into the bottle and add 2 disinfection tablets Shake the bottle until the tablet s are dissolved Thereafter press the OK but...

Page 21: ...bracket and unscrew the original cap from the polyethylene container 2 Pull off the SOLDOS polyethylene container connec tion from the suction line nipple 3 Screw the polyethylene container connectio...

Page 22: ...f the plastic containers or directly into the floor drain CAUTION Ensure that no persons remain in the respective room 2 Press the OK button to activate disinfection 3 The dosing pump starts up and th...

Page 23: ...retain it for the next disinfection Connect a new unused brine polyethylene container with 5 brine solution to die dosing line See Section 5 2 1 1 Place the brine container onto the SOLDOS Thereafter...

Page 24: ...he nozzle of the respective room after rinsing was successful It is recommended to clean the room thereafter The device is now appropriately disinfected and rinsed and therefore ready for operation Ri...

Page 25: ...persons remain in the room concerned Connect the nozzle adapter 19 of the disinfection set supplied 18 to the nozzle in the appropriate room and duct the exuding solution into one of the plastic cont...

Page 26: ...of 70 The rinsing process is completed Rinsing must be repeated in the event of a fault message Remove the nozzle adapter 19 on the nozzle in the respective room after rinsing was successful It is re...

Page 27: ...ion can be started once all commissioning preparations have been completed CAUTION Disinfection as described in Section 5 2 1 Disinfecting and rinsing the Soldos V3 must be performed and documented du...

Page 28: ...uctions no BA DW 005 03 Soldos V3 EN docx Page 28 of 70 A touch screen stylus is included in the delivery scope to make usage easier and protect the touch display Controller menu structure Overview ma...

Page 29: ...Type Soldos V3 Index 03 Change date 01 03 2017 Operating instructions no BA DW 005 03 Soldos V3 EN docx Page 29 of 70 Operating modes sub menu Settings sub menu Figure 11 Operating modes sub menu Fig...

Page 30: ...menu The main menu is displayed after switching on the device at the main switch located at its side 5 main groups can be selected from the main menu Explanation of the symbols 1 Operating modes 2 Se...

Page 31: ...Level of user rights d 00 00 Countdown to the next dosing time indicator e Day of week date time The navigation field After tapping the input field the font turns white and the navigation field is aut...

Page 32: ...chnicians User level 7 WDT menu 2 Access for company service technicians HINT The pre installed passwords are provided in the operating data sheet in Section 9 4 The respective user level is shown in...

Page 33: ...Touch the Home button to get to the start menu You may choose between 3 operating modes 1 Continuous dosing operating mode 2 Button operating mode 3 External control operating mode The green frame sh...

Page 34: ...h individual day of the week by pressing the corresponding button in the right column Touch the left column of the relevant day of the week to enter starting times and the corresponding parameters The...

Page 35: ...st Start time you can set is 23 30 Otherwise it may overlap with the next day After tapping the input field the font turns white and the navigation field is shown Set the desired values and store them...

Page 36: ...DW 005 03 Soldos V3 EN docx Page 36 of 70 6 4 2 Button operating mode Button operation can be used to determine on which week days and at which times dosing can be started by the guests in the sauna...

Page 37: ...arting times and the corresponding parameters The button menu for each day of the week An empty input template is shown here You can enter 2 different time blocks with their respective parameters The...

Page 38: ...s The device will proceed through the dosing and break times as specified The expiry of this time stops the system It can be restarted after a delay period Save the result with OK After completing the...

Page 39: ...ed to set the time blocks While these time blocks are active the Soldos V3 system is operated by an external system e g a WDT central controller You can set 2 individual time blocks for each day of th...

Page 40: ...he week to enter the starting and stop times The time settings for each day of the week An empty input template is shown here You can enter 2 different time blocks with their respective times External...

Page 41: ...field is shown Set the desired values and store them with OK After completing the input save the values with the SAVE button The controller then asks whether you want to accept the settings for other...

Page 42: ...and sound can be made here One of three settings groups can be selected on the touch screen 1 System menu 2 Dosing 3 Effect sound The button leads to the previous view 6 5 1 System menu One of 9 func...

Page 43: ...70 6 5 1 1 Language Select the preferred language The button leads to the previous view 6 5 1 2 Date time The required date and time can be set by using the arrow keys Save and complete the entry wit...

Page 44: ...saver is dimmed to the Display dimmed value and an automatic logout to user level 0 is performed The button illumination in can be set for the active and inactive button and for the external input Aft...

Page 45: ...sheet in Section 9 4 The values of the following menu ranges are set to factory settings on User Levels 2 and 3 Button operation display and back light splash as well as announcement and heater On Use...

Page 46: ...to be changed User level 1 End user The password must have 4 characters User level 2 Technician 1 The password must have 5 characters User level 3 Technician 2 The password must have 6 characters Use...

Page 47: ...Page 47 of 70 6 5 1 6 Network This function is currently not active 6 5 1 7 WDT Menu 1 The operator has reading rights for this menu Changes may only be performed by the WDT company customer service 6...

Page 48: ...menu The Dosing menu is used to set the brine dosing parameters Pre indication Set the time for announcement by action e g light here Announcement means that an action is triggered to announce the up...

Page 49: ...d is shown Set the desired values and store them with OK Confirm with OK or terminate with ESC The button leads to the previous view Repeated request to save 6 5 3 Effect illumination and sound menu I...

Page 50: ...nouncement setting in the dosing menu see Section 6 5 2 Dosing Dosing duration The time is taken from the dosing time setting in the Dosing menu see Section 6 5 2 Store the data with SAVE once the ent...

Page 51: ...rovided to the input a 0 is shown If the electrical input is closed than an electrical signal is provided to the input a green 1 is shown Explanation Button A signal from the button is provided only w...

Page 52: ...timer counts from 30 seconds to 0 An electrical signal is provided at the output during this time A consumer connected to this output will operate during these 30 seconds Press the Button Test to can...

Page 53: ...test is running The test was successful HINT In the event of a fault message see Section 7 3 Fault removal fault codes 6 6 4 Perform disinfection See Section 5 2 1 Disinfection and rinsing of the Sold...

Page 54: ...c logout The display switches to the screen saver when a selectable time period has expired After a further minute has elapsed the screen saver is dimmed and an automatic logout to user level 0 is per...

Page 55: ...ocol in Section 9 5 CAUTION Disinfection must be performed whenever the polyethylene container is changed but at least every 28 days 2 Regular cleaning of the device Brine water leaves ugly stains and...

Page 56: ...DW 005 03 Soldos V3 EN docx Page 56 of 70 Message 1 Disinfection pre indication Pre indication of disinfection You can perform the disinfection already The pre indication is repeated after 1 day Messa...

Page 57: ...nge date 01 03 2017 Operating instructions no BA DW 005 03 Soldos V3 EN docx Page 57 of 70 Message 4 Disinfection has failed polyethylene container empty The disinfection must be repeated Message 5 Ov...

Page 58: ...y pattern Nozzle encrusted Clean nozzle Check brine level in the polyethylene container Top up polyethylene container and check pressure sensor Leaking pipes Check the device for leaks Pump has no pow...

Page 59: ...ne at start up Blow all lines clear with compressed air when shutting down Disposal of old part and operating materials Thoroughly clean disassembled contaminated parts before disposing of them Used p...

Page 60: ...Brine Nebulization System Type Soldos V3 Index 03 Change date 01 03 2017 Operating instructions no BA DW 005 03 Soldos V3 EN docx Page 60 of 70 9 Documents 9 1 Declaration of conformity...

Page 61: ...7 Operating instructions no BA DW 005 03 Soldos V3 EN docx Page 61 of 70 9 2 Terminal plans Note regarding terminal plans The special terminal plans adapted to optional equipment of the Brine nebuliza...

Page 62: ...Brine Nebulization System Type Soldos V3 Index 03 Change date 01 03 2017 Operating instructions no BA DW 005 03 Soldos V3 EN docx Page 62 of 70...

Page 63: ...DW 005 03 Soldos V3 EN docx Page 63 of 70 9 3 Commissioning protocol instruction This protocol is to be completed by the commissioning technician All warranty claims expire when no completed and signe...

Page 64: ...on 1 active inactive 100 10 0 100 0 100 1 Background lighting Button 2 active inactive 100 10 0 100 0 100 1 Password allocation Password guest No password Password final customer 0123 0000 9999 Passwo...

Page 65: ...ground lighting Button 2 active inactive 100 10 0 100 0 100 1 Password allocation Password guest No password Password final customer 0123 0000 9999 Password technician 1 01234 00000 99999 Password tec...

Page 66: ...Maintenance protocol The maintenance protocol is included in the documents attached ATTENTION Disinfection is required at each polyethylene container change and at least every 28 days Maintenance of...

Page 67: ...d in Section 5 2 1 Disinfecting and rinsing the Soldos V3 is performed and documented in the disinfection protocol at least every 28 days It must furthermore be documented when the device is out of op...

Page 68: ...O board 24341 Controller SSD Touch 3 2 24305 Touch input stylus 24168 Dosing technology 3 Membrane pump NF1 25 for Soldos 24269 11 Pressure sensor C08 24256 11 Adapter pressure sensor dia50 1 4 Sole 2...

Page 69: ...kg polyethylene container 17519 5 brine in 5 kg polyethylene container 17613 5 brine in carton 6x1 kg 17669 5 brine in carton 6x5kg 17667 Disinfection 1 SOLDOS disinfection tablet 19871 5 SOLDOS disin...

Page 70: ...Brine Nebulization System Type Soldos V3 Index 03 Change date 01 03 2017 Operating instructions no BA DW 005 03 Soldos V3 EN docx Page 70 of 70 10 Appendices Own notes...

Page 71: ...work 1 Soldos V3 1 1 Perform disinfection at each polyethylene container change and at least every 28 days see disinfection protocol 1 2 Check membrane pump for function and leak tightness 1 1 3 Check...

Page 72: ......

Page 73: ...erating instructions Section 5 2 1 was performed 1 7 Filling and starting of the brine nebuliser was performed according to operating instructions Section 5 2 2 1 8 Control parameters were adapted and...

Page 74: ...Commissioning protocol IP 09 Soldos V3 Z org wdt 02 Qualit tsmanagement ISO 9001 MS Originale Formuale Pr fbericht etc WDT Inbetriebnahmeprotokoll IP WDT IP 09 Soldos V3 EN FO 01 doc Page 2 of 2...