5-48
BA ET18, 20, 24 en* 1.5 * et18_20_24b510.fm
5 Operation
Retrofitting a bucket
Removing
1. Lower the bucket to level ground with the flat side facing downward.
2. Stop and park the machine. Stop the engine. See “Preparing
lubrication”.
3. Remove linch pins
A
.
4. First remove the bolt
B
, then bolt
C
; carefully drive out seized bolts with
a breaker and brass punch.
If pin
C
is stuck:
1. Start the engine.
2. Slighty raise and lower the boom to take the load off the pin.
3. Stop and park the machine. Stop the engine. See “Preparing
lubrication”.
4. Raise the control lever base.
5. Remove the starting key and carry it with you.
Information
Place the bucket only with minimum pressure on the ground as you
remove the pins. The higher the pressure on the ground, the higher the
resistance and the more difficult it is to remove the pins.
Mount
1. Install a bucket only if it is positioned on level ground with the flat side
facing downward.
2. Stop and park the machine. Stop the engine. See “Preparing
lubrication”.
3. Apply grease to the pins and joints before inserting the pins.
4. Start the engine.
5. Straighten the stick so that bores
D
and
E
are flush.
6. Stop the engine. Raise the control lever base.
7. Insert pin
F
.
8. Actuate the stick cylinder until bores
H
and
I
are flush.
9. Stop the engine. Raise the control lever base.
10.Insert pin
J
.
Install linch pins
K
.
Fig. 198Removing
A
C
B
Fig. 199Mount
D
K
F
E
H
I
J
K
Summary of Contents for ET12 02
Page 8: ...EG 4 BA ET18 20 24 en 1 5 et18_20_24konf fm Declaration of conformity Notes...
Page 16: ...1 8 BA ET18 20 24 en 1 5 et18_20_24v100 fm 1 Foreword Notes...
Page 48: ...3 12 BA ET18 20 24 en 1 5 et18_20_24e300 fm 3 Introduction Warning labels Cabin Canopy...
Page 53: ...BA ET18 20 24 en 1 5 et18_20_24e300 fm 3 17 Introduction 3 Information labels...
Page 60: ...3 24 BA ET18 20 24 en 1 5 et18_20_24e300 fm 3 Introduction...
Page 104: ...4 44 BA ET18 20 24 en 1 5 et18_20_24i400 fm 4 Putting into operation...
Page 118: ...5 14 BA ET18 20 24 en 1 5 et18_20_24b510 fm 5 Operation...
Page 170: ...5 66 BA ET18 20 24 en 1 5 et18_20_24b510 fm 5 Operation Notes...
Page 178: ...6 8 BA ET18 20 24 en 1 5 et18_20_24t600 fm 6 Transport...
Page 230: ...7 52 BA ET18 20 24 en 1 5 et18_20_24w710 fm 7 Maintenance Notes...
Page 280: ...9 48 BA ET18 20 24 en 1 5 et18_20_24t900 fm 9 Technical data Notes...