6.
Reverse procedure to install the replacement
burner.
NOTE:
Ensure that burner positioning bracket (U
shaped end) is inserted into slot at the rear of the
burner chamber.
NOTE:
When installing current production burner
covers:
•
Lay cover flat over burner with openings
aligned behind ignitor.
•
Push burner into unit and flip cover 90° up
and align mounting holes.
CURRENT PRODUCTION UNIT SHOWN
7.
Check for proper operation.
GAS ORIFICE
Disconnect the
electrical power to the machine and
follow lockout / tagout procedures.
SHUT OFF THE GAS BEFORE
SERVICING THE UNIT.
1.
Remove the Bottom Front Cover.
2.
Remove the bolts securing the gas manifold to
the oven and place the manifold to the side.
Fig. 18
3.
Remove the gas orifice from the spud on the
manifold and replace with the correct orifice for
the given altitude.
Fig. 19
4.
Reverse procedure to install and check for proper
operation.
GAS SOLENOID VALVE
Disconnect the
electrical power to the machine and
follow lockout / tagout procedures.
SHUT OFF THE GAS BEFORE
SERVICING THE UNIT.
1.
Remove the CONTROL PANEL and the RIGHT
SIDE PANEL.
NOTE:
if right side panel is not accessible, this
component can be serviced by removing the
CONTROL PANEL.
2.
Disconnect the lead wires.
3.
Disconnect the compression fittings to the valve.
VC4G & VC6G SERIES FULL SIZE CONVECTION OVENS - REMOVAL AND REPLACEMENT OF PARTS