Step 5: Insert the sealing caps provided into unused DC connectors on the inverter.
7.
Commissioning
Step 1: Check the following requirements before commissioning:
Ensure the inverter is firmed secured
Check if the open circuit DC voltage of PV module meets requirement (Refer to Section
6)
Check if the open circuit utility voltage of the utility is at approximately same to the
nominal expected value from local utility company.
Correct connection to grid
Full connection to PV modules
Unused DC input connectors are sealed with supplied sealing plugs.
AC circuit breaker and DC circuit breaker are installed correctly.
Step 2: Switch on the AC & DC circuit breakers. All three LEDs will light up. Then:
If green LED lights up, commissioning has been successfully.
Or, if yellow LED lights up, there is insufficient radiation and the inverter is in standby
mode. Wait for sufficient radiation.
CAUTION: Never
disconnect
running inverter
from AC Grid. If it’s necessary to turn off the
inverter, disconnect the AC breaker first and then DC breaker next.
CAUTION: Never
directly touch terminals of the inverter. It will cause lethal electric shock.