VIVREAU BOTTLING SYSTEM 

COMMISSIONING INSTRUCTIONS

Confirm that the proper services are available. The water must be a ½” water line with a ½” 

threaded ball valve female end. Anything smaller than ½” is not acceptable and should 

never be used. The electrical outlet must be within the range of the power cord of the 

machine, extension cords should never be used. CO2 is also provided by the customer in 

either a tank or with a line from a bulk or remote system. If connecting to an existing 

system the customer must provide a ¼” barbed shutoff within 40” of the installation.

If any of the required services are missing/incorrect or if you have any questions regarding 

the  commissioning  instructions,  please  call  877-999-1044  option  #5, and someone from 

our Tech Support Team will provide further instructions.

Open packaging and check for any damage, check the front feet are in a level position.     

Do not connect the machine to the electrical supply just yet. 

Remove rear top access panel and gain access to chiller water bath. ( Figure 1)

Assemble and install Tap Font using supplied installation kit. *V3-202 taps must be directly 

above the system, tap lines should never be extended. 

Connect Water line to street water outlet using supplied kit and diagram. Water supply 

must be 1/2" supply.

Fill chiller water tank until the water level overflows into the waste container. 

(Figure 1)   

Connect street water pipe to the machine and insulate the pipe fully, but  do not  turn the 

water on just yet.   A minimum water supply of 55psi should be supplied to the machine or 

the dispense operation will become slow and may need 

a booster pump.  (Figure 3)