6.
Check the supply (flow) pressure; it
should be
&
20 mbar for natural gas,
&
50 mbar for LPG.
Note
Use suitable test equipment with a
resolution of at least 0.1 mbar to
measure the supply pressure.
Record the actual value in the ser-
vice report.
Take the action shown in the table.
Supply (flow)
pressure for nat-
ural gas
Supply (flow)
pressure for
LPG
Remedy
below 17.4 mbar
below 42.5 mbar
Do not start up. Notify your mains gas or
LPG supplier.
17.4 to 57.5 mbar
42.5 to
57.5 mbar
Start up boiler.
in excess of
57.5 mbar
in excess of
57.5 mbar
Install a separate gas governor down-
stream of the system and regulate the
pressure to 20 mbar for natural gas, or
50 mbar for LPG. Notify your mains gas
or LPG supplier.
7.
Shut down the boiler, close the gas
shut-off valve, remove the pressure
gauge, and close test nipple
A
with the screw.
8.
Open the gas shut-off valve and
start the boiler.
Danger
Gas escaping from the test
nipple leads to a risk of
explosion.
Check test nipple
A
for
soundness.
Further details regarding the individual steps
(cont.)
14
Initial start-up, inspection, maintenance
56
92
548
GB
Summary of Contents for VITODENS 333
Page 114: ...Parts lists cont 114 Parts lists 5692 548 GB ...
Page 115: ...Parts lists cont 115 Parts lists 5692 548 GB ...
Page 116: ...Parts lists cont 116 Parts lists 5692 548 GB ...
Page 117: ...Parts lists cont 117 Parts lists 5692 548 GB ...
Page 118: ...Parts lists cont 118 Parts lists 5692 548 GB ...
Page 119: ...Parts lists cont 119 Parts lists 5692 548 GB ...
Page 131: ...131 5692 548 GB ...