129
Fax the following request, together with the enclosed system scheme, to your local Viessmann sales office.
A competent employee must be present when the system is commissioned.
System details:
Requester
System location
Tick check list boxes:
=
Hydraulic scheme for heating system included
=
Heating circuits fully installed and filled
=
Electrical installation completed
=
Hydraulic lines fully thermally insulated
=
Installation completed in full up to refrigerant circuit
=
All windows and external doors sealed
=
Components for cooling mode fully installed (optional)
=
Components for ventilation fully installed (optional)
=
Components for PV system fully installed (optional)
Preferred appointment:
1.
Date
Time
2.
Date
Time
The work that is requested to be carried out by Viessmann will be billed in accordance with the latest Viessmann
pricelist.
Place / Date
Signature
Final decommissioning and disposal
Viessmann products can be recycled. Components
and substances from the system are not part of ordi-
nary household waste.
For decommissioning the system, isolate the system
from the power supply and allow components to cool
down where appropriate.
All components must be disposed of correctly.
Appendix
Commissioning order
5776 028 GB
Appendix
Summary of Contents for AWT 221.A04
Page 77: ...77 Maintenance Checking the fuses cont 5776 028 GB Maintenance...
Page 87: ...87 Indoor unit parts lists Indoor unit hydraulics cont 5776 028 GB Components...
Page 90: ...90 Indoor unit parts lists Indoor unit cylinder cont 5776 028 GB Components...
Page 137: ...137 Wind direction 11 Wind loads 11 Keyword index Keyword index cont 5776 028 GB...
Page 138: ...138 5776 028 GB...
Page 139: ...139 5776 028 GB...