3.
OPERATION
Once the unit has completed its boot-up sequence and starts running in
Monitoring
mode, press the
MENU
button to toggle between
Monitoring
and
Menu
modes. The Menu mode gives access to the configuration
menu for reviewing or changing the unit’s configuration parameters.
3.1 Startup (boot-up sequence)
When power is applied, the ZPU-5000 searches its internal memory for stored firmware and the last
configuration information used. When required, a modified configuration or additional firmware can later be
uploaded from the ZOOM server, or imported from a prepared USB key. The entire boot-up sequence can last
up to 2 minutes.
1. When power is initially applied, the front panel
display is blank and the front panel LED
indicators display the initial colors:
SYSTEM OK: Yellow
CHANNELS OK: Yellow
ALARM ACKNOWLEDGE: Orange
CHANNELS ALERT / DANGER: Red
2. A message appears on the front panel display
to announce the start of the boot-up sequence.
The LEDs will change color as the boot-up
sequence progresses.
3. The ZPU-5000 address is displayed, and all
applicable service plug-ins are started.
28