controller also supports rectifier temperature compensation if the system is equipped with a temperature
probe(s). Temperature probe(s) may also be designated to monitor ambient temperature and/or battery
temperature. The controller also provides data acquisition, system alarm management, and advanced battery
and energy management. The controller contains a color LCD display and keypad for local access. The
controller provides an Ethernet port and comes with comprehensive webpages for remote access. The
controller has SNMP v3 capability for remote system management. The controller supports software upgrade
via its USB port. Refer to the NCU Controller Instructions (UM1M830BNA) for more information.
Expansion Rectifier Module Mounting Shelf
The system contains one or more expansion rectifier module mounting shelves, each of which houses up to six
(6) rectifier modules. Refer to Power Data Sheet PD588705000 for more information.
Rectifier Modules
The system contains rectifier modules, which provide load power, battery float current, and battery recharge
current during normal operating conditions. Refer to the Rectifier Instructions (UM1R483500E) for more
information.
INSTALLATION ACCEPTANCE CHECKLIST
Provided in this section is an Installation Acceptance Checklist. This checklist helps ensure proper installation
and initial operation of the system. As the procedures presented in this document are completed, check the
appropriate box on this list. If the procedure is not required to be performed for your installation site, also
check the box in this list to indicate that the procedure was read. When installation is done, ensure that each
block in this list has been checked. Some of these procedures may have been factory performed for you.
NOTE!
The system is not powered up until the end of this checklist.
NOTE!
Some of these procedures may have been performed at the factory for you.
Installing the System
Relay Rack Secured to Floor
System Components Mounted in Relay Rack and Interconnected (if required)
Setting Switch Options
Factory Switch Setting on IB2 Interface Board Verified
Making Electrical Connections
Relay Rack Grounding Connection (Frame Ground) Made
AC Input and AC Input Equipment Grounding Connections Made
External Alarm, Reference, Monitoring, and Control Connections Made
Controller Ethernet Connection Made (if required)
-48V DC Output Connections Made