The complete Customer Documentation Package consists of…
System Installation Manual
•
Power System Installation Instructions: Section 6009
System User Manual
•
Power System User Instructions: Section 6010
•
Rectifier Instructions: UM1R482000e
•
Power System “System Application Guide”: SAG582136700
•
Engineering Drawings
Controller User Manual
•
NCU Controller User Instructions: UM1M830BNA
•
ACU+ Controller User Instructions: UM1M820BNA
•
SCU+ Controller User Instructions: UM1M521BNA
•
For factory settings of all configurable Controller parameters, refer to the Configuration Drawing (C-
drawing) supplied with your Power System.
INSTALLATION ACCEPTANCE CHECKLIST
Provided below is an Installation Acceptance Checklist. This checklist helps ensure proper installation and
initial operation of the system. As the procedures presented in this document are completed, check the
appropriate box on this list. If the procedure is not required to be performed for your installation site, also
check the box in this list to indicate that the procedure was read. When installation is done, ensure that each
block in this list has been checked. Some of these procedures may have been factory performed for you.
NOTE!
The system is not powered up until the end of this checklist.
NOTE!
Some of these procedures may have been performed at the factory for you.
Installing the System
Relay Racks (if required) Secured to Floor
Power/Distribution Shelf Secured to Relay Rack or Cabinet
Circuit Breakers Installed
Fuses Installed