4.7
Reversing the Hinge Side of the Enclosure’s Front Door
Refer to Method of Procedure (MOP13).
5
Installation Considerations
NOTE!
If holes are drilled into the exterior of this enclosure and not filled using a seal tight connector, the manufacturer’s
warranty will be void.
5.1
Important Safety Instructions
DANGER!
Adhere to the “Important Safety Instructions” presented at the front of this document.
5.2
Installation Overview
The following is the recommended sequence for the installation and start-up procedures. The sequence may change according to job
and site conditions.
•
Ensure all site drawings and approvals are in place.
•
Obtain the recommended tools and test equipment.
•
Read “Important Safety Instructions” starting on page vii carefully.
•
Check that all the equipment and materials have been delivered.
•
Proceed with the physical installation of the enclosure.
•
Install and verify ground cables.
•
Install and verify the AC power.
•
Install and verify the DC power.
•
Route, splice, and verify the OSP cables.
•
Install and verify the alarm cables.
•
Install and verify the batteries.
•
Turn-up, verify, and adjust the system.
5.3
Tools and Test Equipment Required for Installation
The following tools, test equipment and materials are required for the physical installation of the enclosure:
•
Can wrench; 3/8”and 7/16” (which is traditionally provided with such enclosures)
•
Non-contact voltage detector
•
Digital multimeter (DMM), 0 to 200 V dc, 0 to 300 V ac
-
Digital clamp-on meter, 0 to 30 A dc, 0 to 60 V ac, recommended